Which Project Delivery Method Is Best for Your Project and Why

이 아티클 공유하기

One of the first questions owners face at project onset is which project delivery method to use. Design-Bid-Build (DBB) is slowly becoming extinct, especially for large, complicated projects with challenging schedules. Construction Manager at Risk (CMAR) is a more attractive method, even though it doesn’t quite describe how we work. Design-Build (DB) is on the rise, but many owners still feel like they are paying a premium by preselecting the team. Lastly, Integrated Project Delivery (IPD) still leaves a lot to be desired, as most of the owners are still not willing to share the risk but expect the benefits. 

This article provides an overview of these methods, including contractual obligations and instruments of service and liability; collaboration and use of technology; roles and responsibilities; and budget and scheduling considerations. It provides a foundation for the roundtable discussion that considers the future of project delivery in AEC. 

Part 1: Overview of Project Delivery Methods

There are a lot of options for owners to choose from when it comes to project delivery and procurement methods. Ultimately, they determine how and when they spend their money. Every procurement method has pros and cons, and may be considered a viable option that suits the needs of any given project.

Want to share your knowledge?
Write an article for AU

A lot has been written about each and every one of the procurement methods. From official AIA contract documents and general conditions to various industry expert blogs, you will likely find similar appreciation for and criticism of each of the methods. What follows is not meant to be an exhaustive summary of each of the delivery methods, but a conversation starter focusing on some of the key highlights of each.

Design-Bid-Build 

Design-Bid-Build is perhaps one of the most traditional project delivery methods, used before the age of BIM and the tools and technologies commonly found on job sites today. It is potentially the simplest procurement method as it is very linear. Design is a distinctive phase and is completed to 100% before the projects are bid and awarded, followed by the construction phase.

DBB Contractual Agreements

  • Owner contracts with architect; architect contracts with consultants/engineers

  • Owner contracts with general contractor (GC) after 100% design is complete; GC collects bids from, and contracts with, subcontractors

DBB Benefits

  • Very simple for owners that do not have design/construction experience

  • Competitive cost nature: contractors are bidding against each other to win the project

  • Procurement method of choice for federal projects where three bids are a requirement

DBB Drawbacks

  • Slow project delivery: design needs to be 100% done before construction can begin

  • Lack of constructibility: project is strictly design intent until bid since the design is completed in a silo from construction

  • Lack of cost certainty during design and risk of project being over budget

  • Lack of design optimization with construction insights

  • Finger-pointing between designers and contractors during any conflicts

  • Guarded approach to conflicts and project changes: designers and contractors are on the opposite teams often working against each other, not together

  • Low cost transparency since most projects are lump-sum

  • High cost of non-optimal activities (RFIs, ASIs, rework, conflict resolution, change orders, etc.)

Construction Manager at Risk 

Construction Manager at Risk (CMAR) is a very popular type of a construction management project delivery method in which the construction manager is hired by the owner early during the design phase of the project and integrated as part of the project delivery team. The construction manager (CM) provides constructibility and cost insights as part of their preconstruction services. They typically on-board major trade subcontractors (mechanical, electrical, plumbing, structural) during the design process and involve them into varied forms of a “design assist” process with the design architects and engineers. The construction team is able to establish a Guaranteed Maximum Price (GMP) during the design phase, and start the construction process before the design is 100% complete.

CMAR Contractual Agreements

  • Owner contracts with architect; architect contracts with consultants

  • Owner contracts with CM during early design phase; CM selects major trade subcontractors, develops the GMP and starts construction prior to 100% design completion

CMAR Benefits

  • CM is at risk, so they have incentives to act at the owner’s interest and efficiently manage the cost and schedule

  • Construction can progress more rapidly and in parallel to the design process, resulting in faster speed to market and lower general conditions cost

  • Increased collaboration between the design and construction teams through design assist

CMAR Drawbacks

  • Since the GMP is established early in the process, there is no competitiveness in the process and the owner is not sure if they are getting the best price

  • If the project is at risk of going over budget, the CM will typically respond by trying to reduce scope and/or lower quality

  • There is a lot of overlap in responsibilities (and duplicated work) between designers and trade subcontractors, that the owner pays for

  • Potential for conflicts between design intent and constructibility since they are often occurring parallel to each other

Design-Build 

Contrary to the common belief that Design-Build (DB) is a fairly recent project delivery method due to the rapid increase in popularity over the past 15 years, Design-Build is a very old procurement method reaching back to one of the oldest forms of construction, the concept of master builder. There are many different forms of Design-Build approach, typically sorted into contractor-led or architect-led. Within those two distinct forms, the architect can either work for the contractor, be in a joint venture with the contractor, or be a full-service contractor providing design services as well as construction services.

DB Contractual Agreements

  • Owner enters into a single set of integrated contracts with the design-builder

DB Benefits

  • Single point of responsibility for both design and construction

  • Faster and more integrated design and construction

  • Reduced amount of coordination issues

  • Collaborative approach to project delivery and conflict resolution

  • Increased ability to control the budget

DB Drawbacks

  • Limits the Owner’s involvement in design – sacrifices in design quality/creativity

  • Contractors making design decisions that should be made by designers

  • Lack of competitive nature – owners not sure if they are getting the best price

  • Lack of checks and balances – potential for quality to suffer

  • Depends heavily on trust in the Design-Build contractor

Integrated Project Delivery 

Perhaps one of the most recent project delivery methods, Integrated Project Delivery (IPD) evolved over the last 20 years along with implementation of technology into the world of design and construction, as well as the constant strive to improve efficiency through lean construction. The objective of IPD is to involve all key participants in a collaborative environment, and leverage technology and innovation to increase productivity, reduce waste, avoid overruns, improve quality, and reduce conflicts between owners, architects, engineers, and contractors.

IPD Contractual Agreements

  • Typically, all major parties including owner, architect, engineers, contractor, and major trade subcontractors all enter into an agreement together with the intent on sharing risk and rewards

IPD Benefits

  • Tailored to take full advantage of BIM and VDC technology

  • When executed successfully, tremendous savings of cost and time

  • Improved construction quality

  • Significantly reduced amount of rework and conflicts

  • Collaborative resolution of conflicts since all parties suffer when there are outstanding conflicts

  • Project success depends on success of each and every party in the delivery team

IPD Drawbacks

  • Success heavily relies on trust, which is typically not the starting point

  • Team members are selected on qualifications, not cost

  • Lack of consistency in IPD contracts – almost every IPD contract is fairly unique

  • Owners are hesitant to participate in sharing the risk with the designer and contractors

  • Increased amount of coordination requires more labor than traditional delivery

  • Not as well suited for simple projects as for repetitive, large, complex projects

Part 2: Contractual Obligations, Instruments of Service and Liability

Even though there are a lot of similarities between contract documents and contractual obligations between owners, architects, engineers, contractors and subcontractors, there are also a lot of differences that stem from the very nature of each type of project delivery.

Design-Bid Build 

DBB is a very traditional delivery method with very clear and distinct obligations set forth by the AIA document A201, general conditions of the contract for construction. Architects and engineers are responsible for delivering construction documents (2D drawings) and specifications as basis for bidding the construction of the project. Means and methods strictly lie in the contractor’s scope of work, and so does the production of shop drawings and submittals. Architects and engineers of record are liable for the design of the project, and the contractors are liable for the construction of the projects. When conflicts arise, there is always finger-pointing on whether the conflict resulted from errors and omissions of the design team, or construction coordination by the construction team.

CMAR

Similarly to DBB, CMAR is fairly similar to DBB in terms of contractual obligations and liability. In some instances where the design assist (DA) process is more evolved, the DA subcontractor may actually finish the design and become the engineer of record (EOR) and assume liability for both the design and construction of the engineering systems. Due to the varying nature of CMAR contracts, the general conditions of the contract are often modified to reflect the nature of the specific project delivery approach. The instruments of Service are often the same as DBB, 2D construction documents and specifications, even though some project teams opt into sharing 3D design intent BIM models with heavy “not for construction” disclaimers to protect the liability of the design team.

Design-Build 

Since the design and construction teams are jointly liable for all aspects of the project, they work a lot more collaboratively together. The same entity provides both the design and construction of the project, allowing them to blur the lines between design and construction and achieve many efficiencies that way. They typically work collaboratively in 3D BIM models and produce 2D documentation only for the purpose of obtaining building permits and other necessary reviews by Authorities Having Jurisdiction (AHJs).

Integrated Project Delivery 

Similar to DB, the project team works collaboratively together and is jointly liable for all aspects of the project. Unlike DB, the project team includes the owner who shares in the risk and liability for the project as an equal part of the project delivery team. IPD lends itself to 3D BIM modeling and deep integration of technologies in project delivery. Instruments of service vary, but typically include various forms of 3D BIM models co-authored by the entire project team.

Part 3: Collaboration and Use of Technology

Each of the project delivery methods relies to varied extents on collaboration between owners, designers, and contractors, and leverages technology to different extents in order to successfully deliver the scope of work.

Design-Bid Build 

Use of technology in DBB can be described as siloed at best. There is typically little to no continuation of design technology efforts into construction. Design team chooses their document authoring platforms in a silo without any input or coordination with the contractors and vice versa. Because the instruments of service are still 2D drawings and written specifications, the design team is looking to produce the best set of 2D documents that will serve the project for bidding, and for protecting the design team from any downstream liability. As such, very little attention is given to accurate 3D modeling to allow time for robust 2D detailing and profitability.

Since the construction team only gets the 2D drawings and specifications as their deliverables (or sometimes lower quality 3D models that are specifically marked to be “not for construction"), they typically evaluate their technology approach after bidding, which may include robust VDC services like construction modeling and coordination, laser scanning, field layout, etc. Unfortunately, all of the 3D modeling has to start from scratch which is a tremendous work redo effort costing the project significant time and money.

CMAR

Unlike DBB, the use of technology in the CMAR procurement method is typically a bit more streamlined. Since the construction team is onboarded during the early design phase, there is a varied amount of technology coordination based on several factors including technical prowess of the project teams, levels of comfort and trust between the team members etc. The sliding scale on use of technology is vast, going from barely using technology at all and delivering the project similar to DBB to very technically savvy delivery teams working in near-IPD type setting, under CMAR contracts.

Though there still typically isn’t any 3D model co-authoring, a lot more attention is given to 3D design coordination reviews including trade subcontractors that provide input to the design team via regular design assist meetings. Unfortunately, since the instruments of service are still 2D, any construction modeling efforts typically start from scratch, but at least with some constructibility intelligence coming from the design phase. The level of construction phase technology use varies with the technical capabilities of the construction team, but typically leverages major VDC technologies especially on large and complex projects.

Design-Build 

Since the complete project liability lies completely with a single Design-Build entity, the use of technology is typically more widespread. The project team can collaboratively make decisions about platforms, tools, roles and responsibilities, and jointly author the instruments of service in whichever way they see fit. This is definitely more streamlined for true Design-Build firms than it is for joint ventures between designers and contractors, where trust and comfort level can still be a critical factor in the success rate of leveraging technology.

Integrated Project Delivery 

Ideally, since the success of any design or construction partner in an IPD depends on the success of the entire project, the use of technology should be carefully planned at project startup to make sure there are no downstream surprises in the overall project approach. However, one of the biggest drawbacks to IPD is that trust is earned over time. Since IPD is geared towards heavy use of design and construction technology at its core, new IPD teams typically experience an adjustment period as they learn the technical capabilities, strengths and weaknesses of the individual team members. If there are some early major challenges or gaps in the originally planned IPD delivery process, this can take a toll on the critical trust component and send the IPD Team into the blame-assessing mode, setting up the entire project for failure.

Part 4: Roles and Responsibilities

Who Is Doing What and Why

Even though the general roles of the owner, architect, engineer, contractor, and subcontractors are fairly consistent, there are very distinct differences in terms of actual responsibilities with regards to process, timing and deliverables between the different types of project delivery.

Design-Bid Build 

DBB is perhaps the simplest and most straightforward procurement method when it comes to roles and responsibilities. The design team is responsible for design and production of construction documents and specifications, review of submittals and shop drawings and other traditional construction administration tasks. Contractors bid the project, are responsible for the construction schedule, means, methods, shop drawings, and submittals. It is a fairly siloed approach to design and construction, but most certainly straightforward.

CMAR

There are a lot of different flavors of CMAR projects, which is where it can get very complicated and either help or hurt the project. Since the design and construction teams are a bit more integrated and they vary in levels of technical capabilities, typically the most technically capable team takes on more responsibilities, like 3D modeling and design/construction coordination, scanning, logistics and 4D model-based scheduling, 5D model-driven Quantity Take-Off (QTO), asset data tracking, design/construction issue tracking, reality capture integration, etc.

It is important to clearly define roles and responsibilities in an overall design/construction/lifecycle BIM execution plan, make sure that all parties are performing the tasks they are responsible for, and most importantly, staying in their lane. Otherwise, there may be parallel efforts occurring between the design and construction partners, without even knowing it is happening, which often leads to costly duplication errors and needs for rework that can derail the project schedule, and cost tremendous amounts of additional money.

Design-Build 

Even though one entity is responsible for both the design and construction of the project, it is equally important to set the clear expectations about roles and responsibilities at project inception. Designers are typically responsible for preliminary design and not all the way to 100% construction document level. When the design is developed enough to convey intent to the owner, the construction team takes over with constructibility and detailing.

Often, the design time, quality, and design transparency are considered the drawbacks to Design-Build, since the team is fairly quick to advance to construction in order to optimize the schedule and cost, and not devote enough time to design exploration and design detailing. In case of joint venture DB teams, setting clear role expectations and adhering to a realistic schedule is critical to project success. Otherwise, the team can resort to parallel efforts which may lead to costly design changes during the construction phase, which has tremendous negative impact on the project budget and schedule.

Integrated Project Delivery 

Roles and responsibilities are of utmost importance in IPD project. Typically, owner, architects, engineers, contractor, and subcontractors are all individual entities with very distinct project roles, and rely on each other to deliver their part accurately, on-time, and on-budget. Goal-setting, communication, and transparency are paramount to project success. Due to the integrated and collaborative nature of this type of project delivery, making certain there are no duplicated efforts and that every party “stays in their lane” is not only important to making sure the work get executed correctly, but also the key ingredient in building Trust between the project team members, which is the primary pre-requisite for IPD project success.

Part 5: Budget and Schedule Considerations

Each of the project delivery methods has very distinct pros and cons when project budget and schedule are considered.

Design-Bid-Build 

Most owners still believe that this is the most economical procurement method due to the competitive nature of the bidding process. Design fees are heavily considered as part of hiring the architects and engineers to provide their traditional (and considered lowest-cost) design and documentation services, and the contractors bid against each other to provide the lowest bid, and win the work. However, there are several inefficiencies with the DBB process that, when considered holistically, may tell a different true story about the total cost of DBB.

First, the delivery process is extended due to the linear nature since the design needs to be 100% completed before bidding the project and starting construction. This may result in revenue loss from slower speed to market. Additionally, since the construction process will likely take longer since the contractors are starting from scratch, the general conditions line item likely costs more. If the project bids over budget, there is a significant value engineering effort that needs to happen, which likely costs additional time and money, and sacrifices the project scope and/or quality.

DBB typically has more non-optimal activities like RFIs and ASIs which cost a lot of time and money to process, and even more money to resolve, often resulting in costly change orders. Because the contractors had to bid as lean as possible to win the project, they are often relying on finding items the design team may have missed on the documents, to request change orders that allow them to build profit back into the project. (There are several books that provide contractors with guidance on change orders.) This is not a collaborative team effort which causes delays and additional budget changes, which typically more than offsets any efficiencies from the lower design fees or the competitive bid process, which can often make this procurement method the most expensive in lieu of most economical.

CMAR

One of the biggest criticisms of CMAR is that the owner is preselecting the team based on qualifications and not based on cost. There is typically no competitive bidding for the major trades as they are locked into the contract early-on, and they work with the construction manager to fit the scope into the agreed-upon GMP. This may cause several issues, like CMs being very conservative while establishing the GMP, leaving the owners wondering if they are getting the best value for their money. Additionally, if there is any indication that the project may go over the agreed-upon GMP due to any unforeseen conditions (or even errors/work redo beyond the planned contingencies), the contractors typically advise towards either reduction in scope or quality.

When things go smoothly, CMAR can provide a great value to the owner and produce very successful project. Likewise, when there are problems, it may leave the owners wondering why they chose to go with this procurement method to begin with. One of the benefits of CMAR is certainly the potential for schedule acceleration compared to DBB. The project is typically executed in multiple bid packages in order to enable parallel design and construction process, as well as optimizing the critical path schedule by evaluating the long lead-time components and making sure there are no bottlenecks to slow down the construction process.

Design-Build 

Cost and time are big drivers of Design-Build projects. The premise is, since the design and construction is done by the same entity, the overall process can advance a lot more rapidly and thus take less time, and cost less money. Design is performed concurrently with construction and with strict budget in mind. Arguably one of the most economical ways to deliver projects, optimizing cost and time often sacrifices the design quality and exploration to fit the owner’s custom needs. Decisions need to be made rather quickly and any changes down the road are typically very costly and sometimes not even feasible due to the amount of cost/time impact, leaving the owner “stuck” with the decisions they made early in the project, when they may not have had all the facts they needed to make those decisions.

Integrated Project Delivery 

Even though IPD is geared towards leveraging technology and lean processes to reduce waste and improve efficiency, the amount of time spent communicating and collaborating between all of the different parties creates a very labor-intensive process. Design and construction optimization from the collaborative nature of this project delivery method is designed to offset the additional labor needed, and produce leaner and more efficient projects that are executed with ease. IPD typically delivers projects with less construction waste leveraging a much more coordinated approach, which should result in lower overall construction cost.

Even though advanced and costly technologies are an added cost compared to traditional projects, the time and budget efficiencies they create more than offset the associated hard and soft costs. When delivered successfully, IPD should produce some of the most cost effective and fastest projects, especially for very large, complex and repetitive project types.

Conclusion: Enhanced Delivery Method?

Given this brief overview of the most common project delivery methods, it is clear that there is no “winner” that will prevail over the others for all projects. Does this mean none of the project delivery methods are fully adequate to support how we can best deliver projects, or do we simply need to choose the delivery method that fits the best? Do we need a new project delivery method that would combine the best of all worlds?

Perhaps we are at the brink of developing new procurement methods. Maybe we should consider a "Buildable Design-Bid-Build” project delivery that would blend design intent with construction coordination, means, and methods and retain the competitive bid process, but enable utilization of BIM and VDC to the fullest extent, with little to no loss of project delivery intelligence and minimal work redo. A process that would natively enable precoordination and construction scheduling/logistics during the design phase, and bidding construction installation from shop-drawing-ready models versus 2D construction documents.

What would the contracts look like with this enhanced delivery? How about design fees? Roles and responsibilities? Liability? Rewards and penalties? How about deliverables – would we be delivering much more intuitive digital twins at the end of this enhanced delivery process? 

Watch the roundtable for the related discussion on these project delivery methods, technology-driven delivery, innovation, risks, and constraints on where our built environment industry is inevitably headed.

In his current role at Jacobs, Marin focuses on leveraging his extensive AEC industry experience to help project teams discern project technology and innovation constraints and opportunities. He is passionate about developing the most suitable project execution strategy that leverages advanced Virtual Design and Construction tools and workflows in innovative ways to help streamline the design/construction delivery, and achieve a digital handover of the built environment suitable for the owner’s asset lifecycle operation and management process. He focuses his leadership and advocacy for enhancing the built environment both internally at Jacobs to raise awareness as we Challenge Today and Reinvent Tomorrow, and externally with existing and potential / new clients.

______
icon-svg-close-thick

쿠기 기본 설정

오토데스크는 고객의 개인 정보와 최상의 경험을 중요시합니다. 오토데스크는 정보를 사용자화하고 응용프로그램을 만들기 위해 고객의 본 사이트 사용에 관한 데이터를 수집합니다.

오토데스크에서 고객의 데이터를 수집하고 사용하도록 허용하시겠습니까?

오토데스크에서 사용하는타사 서비스개인정보 처리방침 정책을 자세히 알아보십시오.

반드시 필요 - 사이트가 제대로 작동하고 사용자에게 서비스를 원활하게 제공하기 위해 필수적임

이 쿠키는 오토데스크에서 사용자 기본 설정 또는 로그인 정보를 저장하거나, 사용자 요청에 응답하거나, 장바구니의 품목을 처리하기 위해 필요합니다.

사용자 경험 향상 – 사용자와 관련된 항목을 표시할 수 있게 해 줌

이 쿠키는 오토데스크가 보다 향상된 기능을 제공하고 사용자에게 맞는 정보를 제공할 수 있게 해 줍니다. 사용자에게 맞는 정보 및 환경을 제공하기 위해 오토데스크 또는 서비스를 제공하는 협력업체에서 이 쿠키를 설정할 수 있습니다. 이 쿠키를 허용하지 않을 경우 이러한 서비스 중 일부 또는 전체를 이용하지 못하게 될 수 있습니다.

광고 수신 설정 – 사용자에게 타겟팅된 광고를 제공할 수 있게 해 줌

이 쿠키는 사용자와 관련성이 높은 광고를 표시하고 그 효과를 추적하기 위해 사용자 활동 및 관심 사항에 대한 데이터를 수집합니다. 이렇게 데이터를 수집함으로써 사용자의 관심 사항에 더 적합한 광고를 표시할 수 있습니다. 이 쿠키를 허용하지 않을 경우 관심 분야에 해당되지 않는 광고가 표시될 수 있습니다.

icon-svg-close-thick

타사 서비스

각 범주에서 오토데스크가 사용하는 타사 서비스와 온라인에서 고객으로부터 수집하는 데이터를 사용하는 방식에 대해 자세히 알아보십시오.

icon-svg-hide-thick

icon-svg-show-thick

반드시 필요 - 사이트가 제대로 작동하고 사용자에게 서비스를 원활하게 제공하기 위해 필수적임

Qualtrics
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 Qualtrics를 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. 오토데스크는 이 데이터를 다른 소스에서 수집된 데이터와 결합하여 고객의 판매 또는 고객 서비스 경험을 개선하며, 고급 분석 처리에 기초하여 보다 관련 있는 컨텐츠를 제공합니다. Qualtrics 개인정보취급방침
Akamai mPulse
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Akamai mPulse를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Akamai mPulse 개인정보취급방침
Digital River
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Digital River를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Digital River 개인정보취급방침
Dynatrace
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Dynatrace를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Dynatrace 개인정보취급방침
Khoros
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Khoros를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Khoros 개인정보취급방침
Launch Darkly
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Launch Darkly를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Launch Darkly 개인정보취급방침
New Relic
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 New Relic를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. New Relic 개인정보취급방침
Salesforce Live Agent
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Salesforce Live Agent를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Salesforce Live Agent 개인정보취급방침
Wistia
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Wistia를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Wistia 개인정보취급방침
Tealium
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Tealium를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Upsellit
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Upsellit를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. CJ Affiliates
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 CJ Affiliates를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Commission Factory
Typepad Stats
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Typepad Stats를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Typepad Stats 개인정보취급방침
Geo Targetly
Autodesk는 Geo Targetly를 사용하여 웹 사이트 방문자를 가장 적합한 웹 페이지로 안내하거나 위치를 기반으로 맞춤형 콘텐츠를 제공합니다. Geo Targetly는 웹 사이트 방문자의 IP 주소를 사용하여 방문자 장치의 대략적인 위치를 파악합니다. 이렇게 하면 방문자가 (대부분의 경우) 현지 언어로 된 콘텐츠를 볼 수 있습니다.Geo Targetly 개인정보취급방침
SpeedCurve
Autodesk에서는 SpeedCurve를 사용하여 웹 페이지 로드 시간과 이미지, 스크립트, 텍스트 등의 후속 요소 응답성을 측정하여 웹 사이트 환경의 성능을 모니터링하고 측정합니다. SpeedCurve 개인정보취급방침
Qualified
Qualified is the Autodesk Live Chat agent platform. This platform provides services to allow our customers to communicate in real-time with Autodesk support. We may collect unique ID for specific browser sessions during a chat. Qualified Privacy Policy

icon-svg-hide-thick

icon-svg-show-thick

사용자 경험 향상 – 사용자와 관련된 항목을 표시할 수 있게 해 줌

Google Optimize
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Google Optimize을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Google Optimize 개인정보취급방침
ClickTale
오토데스크는 고객이 사이트에서 겪을 수 있는 어려움을 더 잘 파악하기 위해 ClickTale을 이용합니다. 페이지의 모든 요소를 포함해 고객이 오토데스크 사이트와 상호 작용하는 방식을 이해하기 위해 세션 녹화를 사용합니다. 개인적으로 식별 가능한 정보는 가려지며 수집되지 않습니다. ClickTale 개인정보취급방침
OneSignal
오토데스크는 OneSignal가 지원하는 사이트에 디지털 광고를 배포하기 위해 OneSignal를 이용합니다. 광고는 OneSignal 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 OneSignal에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 OneSignal에 제공하는 데이터를 사용합니다. OneSignal 개인정보취급방침
Optimizely
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Optimizely을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Optimizely 개인정보취급방침
Amplitude
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Amplitude을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Amplitude 개인정보취급방침
Snowplow
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Snowplow를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Snowplow 개인정보취급방침
UserVoice
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 UserVoice를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. UserVoice 개인정보취급방침
Clearbit
Clearbit를 사용하면 실시간 데이터 보강 기능을 통해 고객에게 개인화되고 관련 있는 환경을 제공할 수 있습니다. Autodesk가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. Clearbit 개인정보취급방침
YouTube
YouTube는 사용자가 웹 사이트에 포함된 비디오를 보고 공유할 수 있도록 해주는 비디오 공유 플랫폼입니다. YouTube는 비디오 성능에 대한 시청 지표를 제공합니다. YouTube 개인정보보호 정책

icon-svg-hide-thick

icon-svg-show-thick

광고 수신 설정 – 사용자에게 타겟팅된 광고를 제공할 수 있게 해 줌

Adobe Analytics
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Adobe Analytics를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Adobe Analytics 개인정보취급방침
Google Analytics (Web Analytics)
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Google Analytics (Web Analytics)를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. AdWords
Marketo
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 Marketo를 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. 오토데스크는 이 데이터를 다른 소스에서 수집된 데이터와 결합하여 고객의 판매 또는 고객 서비스 경험을 개선하며, 고급 분석 처리에 기초하여 보다 관련 있는 컨텐츠를 제공합니다. Marketo 개인정보취급방침
Doubleclick
오토데스크는 Doubleclick가 지원하는 사이트에 디지털 광고를 배포하기 위해 Doubleclick를 이용합니다. 광고는 Doubleclick 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Doubleclick에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Doubleclick에 제공하는 데이터를 사용합니다. Doubleclick 개인정보취급방침
HubSpot
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 HubSpot을 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. HubSpot 개인정보취급방침
Twitter
오토데스크는 Twitter가 지원하는 사이트에 디지털 광고를 배포하기 위해 Twitter를 이용합니다. 광고는 Twitter 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Twitter에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Twitter에 제공하는 데이터를 사용합니다. Twitter 개인정보취급방침
Facebook
오토데스크는 Facebook가 지원하는 사이트에 디지털 광고를 배포하기 위해 Facebook를 이용합니다. 광고는 Facebook 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Facebook에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Facebook에 제공하는 데이터를 사용합니다. Facebook 개인정보취급방침
LinkedIn
오토데스크는 LinkedIn가 지원하는 사이트에 디지털 광고를 배포하기 위해 LinkedIn를 이용합니다. 광고는 LinkedIn 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 LinkedIn에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 LinkedIn에 제공하는 데이터를 사용합니다. LinkedIn 개인정보취급방침
Yahoo! Japan
오토데스크는 Yahoo! Japan가 지원하는 사이트에 디지털 광고를 배포하기 위해 Yahoo! Japan를 이용합니다. 광고는 Yahoo! Japan 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Yahoo! Japan에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Yahoo! Japan에 제공하는 데이터를 사용합니다. Yahoo! Japan 개인정보취급방침
Naver
오토데스크는 Naver가 지원하는 사이트에 디지털 광고를 배포하기 위해 Naver를 이용합니다. 광고는 Naver 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Naver에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Naver에 제공하는 데이터를 사용합니다. Naver 개인정보취급방침
Quantcast
오토데스크는 Quantcast가 지원하는 사이트에 디지털 광고를 배포하기 위해 Quantcast를 이용합니다. 광고는 Quantcast 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Quantcast에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Quantcast에 제공하는 데이터를 사용합니다. Quantcast 개인정보취급방침
Call Tracking
오토데스크는 캠페인을 위해 사용자화된 전화번호를 제공하기 위하여 Call Tracking을 이용합니다. 그렇게 하면 고객이 오토데스크 담당자에게 더욱 빠르게 액세스할 수 있으며, 오토데스크의 성과를 더욱 정확하게 평가하는 데 도움이 됩니다. 제공된 전화번호를 기준으로 사이트에서 고객 행동에 관한 데이터를 수집할 수도 있습니다. Call Tracking 개인정보취급방침
Wunderkind
오토데스크는 Wunderkind가 지원하는 사이트에 디지털 광고를 배포하기 위해 Wunderkind를 이용합니다. 광고는 Wunderkind 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Wunderkind에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Wunderkind에 제공하는 데이터를 사용합니다. Wunderkind 개인정보취급방침
ADC Media
오토데스크는 ADC Media가 지원하는 사이트에 디지털 광고를 배포하기 위해 ADC Media를 이용합니다. 광고는 ADC Media 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 ADC Media에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 ADC Media에 제공하는 데이터를 사용합니다. ADC Media 개인정보취급방침
AgrantSEM
오토데스크는 AgrantSEM가 지원하는 사이트에 디지털 광고를 배포하기 위해 AgrantSEM를 이용합니다. 광고는 AgrantSEM 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 AgrantSEM에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 AgrantSEM에 제공하는 데이터를 사용합니다. AgrantSEM 개인정보취급방침
Bidtellect
오토데스크는 Bidtellect가 지원하는 사이트에 디지털 광고를 배포하기 위해 Bidtellect를 이용합니다. 광고는 Bidtellect 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Bidtellect에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Bidtellect에 제공하는 데이터를 사용합니다. Bidtellect 개인정보취급방침
Bing
오토데스크는 Bing가 지원하는 사이트에 디지털 광고를 배포하기 위해 Bing를 이용합니다. 광고는 Bing 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Bing에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Bing에 제공하는 데이터를 사용합니다. Bing 개인정보취급방침
G2Crowd
오토데스크는 G2Crowd가 지원하는 사이트에 디지털 광고를 배포하기 위해 G2Crowd를 이용합니다. 광고는 G2Crowd 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 G2Crowd에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 G2Crowd에 제공하는 데이터를 사용합니다. G2Crowd 개인정보취급방침
NMPI Display
오토데스크는 NMPI Display가 지원하는 사이트에 디지털 광고를 배포하기 위해 NMPI Display를 이용합니다. 광고는 NMPI Display 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 NMPI Display에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 NMPI Display에 제공하는 데이터를 사용합니다. NMPI Display 개인정보취급방침
VK
오토데스크는 VK가 지원하는 사이트에 디지털 광고를 배포하기 위해 VK를 이용합니다. 광고는 VK 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 VK에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 VK에 제공하는 데이터를 사용합니다. VK 개인정보취급방침
Adobe Target
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Adobe Target을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Adobe Target 개인정보취급방침
Google Analytics (Advertising)
오토데스크는 Google Analytics (Advertising)가 지원하는 사이트에 디지털 광고를 배포하기 위해 Google Analytics (Advertising)를 이용합니다. 광고는 Google Analytics (Advertising) 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Google Analytics (Advertising)에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Google Analytics (Advertising)에 제공하는 데이터를 사용합니다. Google Analytics (Advertising) 개인정보취급방침
Trendkite
오토데스크는 Trendkite가 지원하는 사이트에 디지털 광고를 배포하기 위해 Trendkite를 이용합니다. 광고는 Trendkite 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Trendkite에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Trendkite에 제공하는 데이터를 사용합니다. Trendkite 개인정보취급방침
Hotjar
오토데스크는 Hotjar가 지원하는 사이트에 디지털 광고를 배포하기 위해 Hotjar를 이용합니다. 광고는 Hotjar 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Hotjar에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Hotjar에 제공하는 데이터를 사용합니다. Hotjar 개인정보취급방침
6 Sense
오토데스크는 6 Sense가 지원하는 사이트에 디지털 광고를 배포하기 위해 6 Sense를 이용합니다. 광고는 6 Sense 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 6 Sense에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 6 Sense에 제공하는 데이터를 사용합니다. 6 Sense 개인정보취급방침
Terminus
오토데스크는 Terminus가 지원하는 사이트에 디지털 광고를 배포하기 위해 Terminus를 이용합니다. 광고는 Terminus 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Terminus에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Terminus에 제공하는 데이터를 사용합니다. Terminus 개인정보취급방침
StackAdapt
오토데스크는 StackAdapt가 지원하는 사이트에 디지털 광고를 배포하기 위해 StackAdapt를 이용합니다. 광고는 StackAdapt 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 StackAdapt에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 StackAdapt에 제공하는 데이터를 사용합니다. StackAdapt 개인정보취급방침
The Trade Desk
오토데스크는 The Trade Desk가 지원하는 사이트에 디지털 광고를 배포하기 위해 The Trade Desk를 이용합니다. 광고는 The Trade Desk 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 The Trade Desk에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 The Trade Desk에 제공하는 데이터를 사용합니다. The Trade Desk 개인정보취급방침
RollWorks
We use RollWorks to deploy digital advertising on sites supported by RollWorks. Ads are based on both RollWorks data and behavioral data that we collect while you’re on our sites. The data we collect may include pages you’ve visited, trials you’ve initiated, videos you’ve played, purchases you’ve made, and your IP address or device ID. This information may be combined with data that RollWorks has collected from you. We use the data that we provide to RollWorks to better customize your digital advertising experience and present you with more relevant ads. RollWorks Privacy Policy

정말 더 적은 온라인 경험을 원하십니까?

오토데스크는 고객 여러분에게 좋은 경험을 드리고 싶습니다. 이전 화면의 범주에 대해 "예"를 선택하셨다면 오토데스크는 고객을 위해 고객 경험을 사용자화하고 향상된 응용프로그램을 제작하기 위해 귀하의 데이터를 수집하고 사용합니다. 언제든지 개인정보 처리방침을 방문해 설정을 변경할 수 있습니다.

고객의 경험. 고객의 선택.

오토데스크는 고객의 개인 정보 보호를 중요시합니다. 오토데스크에서 수집하는 정보는 오토데스크 제품 사용 방법, 고객이 관심을 가질 만한 정보, 오토데스크에서 더욱 뜻깊은 경험을 제공하기 위한 개선 사항을 이해하는 데 도움이 됩니다.

오토데스크에서 고객님께 적합한 경험을 제공해 드리기 위해 고객님의 데이터를 수집하고 사용하도록 허용하시겠습니까?

선택할 수 있는 옵션을 자세히 알아보려면 이 사이트의 개인 정보 설정을 관리해 사용자화된 경험으로 어떤 이점을 얻을 수 있는지 살펴보거나 오토데스크 개인정보 처리방침 정책을 확인해 보십시오.