Planning for BIM: Using Construction Schedules to Enhance the Coordination Process

이 강의 공유하기

설명

Many BIM execution plans set good requirements for modeling and model management. However, many forget about managing the schedule. This session will focus on how to create and mange a detailed schedule. We will explore strategies and options for telling the BIM coordination story through the schedule using BIM 360 Plan and Microsoft Excel. We will also talk about applying the 6 Ps (Prior Proper Planning Prevents Poor Performance) and how to avoid creating lessons learned by managing the schedule.

주요 학습

  • Learn how to create a coordination schedule in BIM 360 Plan or Excel
  • Learn how to collaborate with stakeholders to build your schedule
  • Learn how to hold stakeholders accountable using the schedule
  • Learn how to start implementing scheduling strategies within your organization

발표자

  • Nick Dyer 님의 아바타
    Nick Dyer
    Nick Dyer received his Bachelor’s Degree in Construction Management from Weber State University. He has been using Building Information Modeling (BIM) technology for the last 14 years and has been applying his knowledge in technology to both the design and construction sides of the industry. Currently, Nick works for Okland Construction as an Integrated Construction Manager working to expand and implement technology on the jobsite through the use of models and reality capture. He is also helping to support new talent in the industry as an adjunct professor at Weber State University and Boise State University along with working beside the local Revit Users Group. Pulling from experience on both sides of the industry, Nick is able to support the BIM process from design to project closeout.
Video Player is loading.
Current Time 0:00
Duration 57:47
Loaded: 0.29%
Stream Type LIVE
Remaining Time 57:47
 
1x
  • Chapters
  • descriptions off, selected
  • en (Main), selected
Transcript

NICK DYER: All right, so they shut the door, so I assume that that means that they want me to get started. [LAUGHS] Hope everybody's doing good. Second day of AU, we're coming down to the end of the day here. This is about the time in the conference when my brain starts to melt a little bit, but thanks for coming. So there's plenty of stuff up here in the front. [LAUGHS] It's best seating in the house.

AUDIENCE: Yep.

NICK DYER: Awesome. So I guess technically we still had a couple minutes, but they shut the door so I guess it threw me off.

All right, so today we're going to be talking about planning for BIM using construction schedules to enhance the coordination process. It's a little bit of a mouthful, I realize that, but basically, what we're going to be talking about is being able to build a schedule that we can then use in order to keep people accountable, build transparency, and enhance that overall coordination process. Because a lot of times what happens is you get a blanket statement, like six weeks in your schedule, and it doesn't really define all of the things that have to go into the coordination effort. So that's what we're going to hopefully discuss here. Also as a quick note, we do have some parts of this that are live demonstrations, so we're going to move through those pretty quick. But if you have any specific questions, we'll wait to the end to do that, and we can go back and re-evaluate some of our stuff.

So my name is Nick Dyer, work for Oakland Construction, have been there for about seven years. And been in their BIM department for pretty much that entire time, working on projects all over the Western United States, mostly in health care, though, there's been a few things mixed in here and there for some different opportunities, some lab spaces and things like that. Overall, it's been pretty good.

Oakland Construction is headquartered out of Salt Lake City, Utah. We do work all over the western United States. And we also have offices in Tempe, Arizona and in Boise, Idaho. And we just broke $1 billion for the second year in a row. So we're pretty excited about that.

So and then, in our BIM tool bag, we use a lot of different tools when we talk about BIM, but today, we're going to focus on BIM 360 Plan. And also, we're going to be using Excel. And really, the only reason we've chosen those is because they're kind of widely easy for people to access.

So we're going to get started with just jumping into building our schedule. Of course, it's the first part of this whole process, and we have a couple of quick videos to comically introduce these subjects so--

[VIDEO PLAYBACK]

[MUSIC PLAYING]

[PHONE RINGING]

- My new five year plan looks like this.

[PHONE RINGING]

- Well, how can you have a five year plan when you don't know what will happen in five minutes?

- We have this room now.

- Bad timing. Shoo, shoo.

[PHONE RINGING]

[BELL RINGING]

[END PLAYBACK]

[LAUGHS]

NICK DYER: And then, just one more here.

[VIDEO PLAYBACK]

[MUSIC PLAYING]

- Do you prefer that I spend the day planning, which doesn't look like work, or should I plunge into my project with aggressive randomness?

- He told you not to work?

- Yeah. He doesn't know it yet.

[BELL RINGING]

[END PLAYBACK]

NICK DYER: [LAUGHS] All right, so when we're planning, we're going to focus on the six P's here. And those six P's are prior proper planning prevents poor performance. Because when we go at things in aggressive randomness, we get a whole lot of random things done, but the whole thing doesn't really come together. And because we haven't planned for it properly. And that's part of the problem that we have with scheduling when we just have blanket statements of we're going to do this in a week, or we're going to do this in two weeks, or something like that. We haven't really built in that level of detail to understand what needs to happen in that period of time.

So when we're selecting a software, I chose today to look at BIM 360 Plan and then also to work through Excel, and only because those things are accessible to people who have access to BIM 360 or just have access to Excel. A lot of people don't have access to or don't know P6, or at least maybe that's just at Oakland, but your company might be different. But it doesn't really matter which one you choose as long as they allow you to make updates so that when you're building your schedule, you're not stuck to a rigid course of activities. And that you're able to go back and add delays. You're able to go in and add roadblocks and those kinds of things so that your schedule is detailed.

The other thing, too, is that you need to be able to share it with people who don't have access to your software, whether that's just a PDF print out, or whether it's Excel, pretty much anyone has access to Excel. Excuse me.

So for this class, we're going to go through a two story medical clinic. Basically, it's meant to just be really easy, but it requires BIM coordination. And it's going to require BIM coordination to a pretty significant level of detail. And we've got an imaging suite. We've got physician's offices, some procedure rooms, and then we have a mechanical penthouse, a pretty typical two story clinic.

So first thing we're going to do is we're going to break this out into stages. Now these stages are the ones that we typically use when we're planning out our coordination schedule. And we start with equipment submittals, move to content modeling, then BIM coordination, shop drawings, and then we're ready for construction. Then we have a construction start. We're going to jump into these phases because we even break these down further into specific activities.

So looking at our master schedule in this scenario, we're going to have these pour dates. Now the reason for these pour dates and why they're important is because at the time that we look at the schedule or at least in this scenario, we don't have an activity for hangar placement. But we need a coordinated model in order to have hangar placement. So we need to beat that day by seven days. That gives time for our trades to be able to say OK, the model coordination is complete. Now we have some time to actually go out and place hangars before the pour happens.

So and it's just from that lack of detail in our master schedule. As we approach closer to that date, our master schedule may include hangar placement. And, at that point, we can update our coordination schedule. But for now, this is where it stands.

So first thing we're going to do, I'm going to jump into Excel really fast and introduce you guys to the Excel spreadsheet that we've got. So this Excel spreadsheet that we're going to be using has everything laid out. Formulas are already built into this and actually in the additional files for this class. I've provided you with the same template. So you can toy around with it as well.

But basically, what we can do in here is that we've got our dates preloaded there on the end, and we're going to pull plan this a little bit. So we're going to start with our seven days and just enter those into the cells. And you can see there that we've got dates starting to auto populate in there. So the same thing, just to give a contrast to BIM 360 Plan, when we pull this one up, we've got our dates added in here already. And if you haven't used Plan, it's another pull planning software, but we're going to use it for planning purposes today.

So for right now, we're just going to add some activities. So it's really simple to do that. We just add a new activity. It brings us to this task bar, preloads in some activities that we've added in the past.

But in this case, we need to just add level one is being ready for construction-- lost my mouse. Ready, and then we said it was going to be seven calendar days, which equates to five business days. Within here, we can eliminate Saturdays, Sundays, and holidays and do calendar days if we want to, but really, it's five working days. Anybody that's done some scheduling can make that conversion pretty fast in their head. But we're going to be doing that in five days.

So then from our schedule, we know that we need to-- we know that that's going to happen. That's the date we have to beat. It gives us our finish date. We need five day duration, and it gives us a start date. We can, if we wanted to, build a work breakdown structure, WBS. In this case, we're not going to just yet.

And then we can add a handoff. Now the handoff is basically what is the next activity. So for this one, we need to start building that logic, and we're going to do the slab on deck pour. Then we can save and add another. This process becomes repetitive, but the nice thing is is that Plan gives us some tools.

So then we know that we need to beat the next one by the next day. And then our handoff is not going to be the level two slab on deck. It's actually going to be our penthouse slab on deck pour. And then so on, down the list.

All right, so we've saved those in there. So now we can start in our Gantt chart. We can start to see that logic starting to be built in here. So somewhere along the way, we ended up with a repeat activity. So we can just get rid of one of those, and then just click delete activity. And now it's gone.

But then also, you see that our pour and our day that we're finishing is the same day. So we probably don't want that. It's really easy to just pull this back a day and snap that into place. And now we're finishing the day before, and then the next morning, they're ready to go. And it's pretty simple to just keep pulling this back and letting that take place.

So for some reason, this one doesn't want to snap to the 10th. So we can actually just come in here and just force our finish date to the 10th, and then it auto updates. So this becomes a pretty powerful little planning tool. Even if your company is not necessarily leveraging pull planning, it allows you, at least, as your coordinator, or the BIM lead, or whatever it is that you call it on your project, an opportunity to come in and build a very detailed schedule within this, with logic and everything like that.

So being that this takes a little bit of time to build here live, we're going to focus mostly on Excel for the rest of the time period to give as much time at the end for questions and that kind of thing. But we can jump into this, and I'm willing to go through any features and that kind of thing with you guys. So jumping back into our presentation here.

So we had this construction start versus ready for construction. And what those basically is is the ready for construction is the day we're ready to go. It's the day we say, "All right, we are finished with our coordination process. Everything is ready for construction." And the construction start is the day that your master schedule says, "This is when the activity is actually ready to go."

So in this case, because our master schedule didn't quite have enough detail to place hangars yet, we're using that time in there to say, "We're going to be placing hangars during this period of time." But really, as our schedule updates and we start getting more meat and potatoes in our master schedule, this time becomes float. And it becomes very easy to manage the amount of float that we have.

So another couple of little videos here to talk about shop drawings. I know this isn't quite related to construction or the coordination process, but I'm sure you guys are smart enough to see the parallels.

[VIDEO PLAYBACK]

- So I'm happy to report we have succeeded in rebooting our flagships. Way ahead of schedule yet again. This has allowed us to improve our USBs by 90%. That's nine out of every 10.

- Excellent. Thank you, Samuel. Timothy, what's the status with the linear solutions? Could you give us the latest on the square project?

- The linear solutions department has yet again functioned at full capacity, and we have fulfilled 114% of this month's objectives. You can read the handouts for a detailed account, but, in short, as I reported last week, we've decided to use the right angle for the square project. Now there's still some debate as to how big a right angle is, so we're testing currently at 90, 97. 100, and 101 degrees. As agreed, I have ensured Anderson cross checks the design, removing any left angles and doesn't use them in future. Overall, we have very good progress with the design.

- Are we on track for the schedule? When are we required to start delivering?

- I'm happy to report that we are ready to start first deliveries tomorrow, which is way ahead of the requested delivery schedule.

- We've only just finished system testing the prototype and are only half way through performance testing. We haven't even released an alpha version yet.

- As I said earlier, we've had very good progress with the design.

- Yes, we've had very good progress, but I'd say the design of the product is only 75% complete.

- Well, exactly. That's three out of every four, so we're ready to start shipping tomorrow.

- What? It doesn't work like that.

- We'll produce, say, four units, but only ship the first three. Then when you're finally 100% complete with the design, we can then ship the fourth.

- Excellent work, Timothy. You can proceed with the production. Anderson, send me please a revised delivery schedule so I can share it with a client. Well, thank you everyone. This was very productive yet again.

[END PLAYBACK]

NICK DYER: So the rest of that video goes into some deep dives. It's actually the third part of a four part series, but basically, that's how BIM gets treated sometimes. It's like hey, did we get the coordination complete? Great, we're ready to rock and roll tomorrow and start Ruffin. We have had no time to create shop drawings. [LAUGHS]

So it's like this. We're only 75% of the way there. It doesn't work like that. We do need time for the shop drawings. It's true that we are building that spine for the shop drawings in the background for our model, it's just that we need to finish up the drafting. But that drafting in those details, that's what the field is actually going to use to make their installation. And it's also the point data that we extract from those that they're probably going to be using if they're using a total station layout system.

So we then split that into shop drawing creation, which is the time to actually build our shop drawings. It's the time to draft in those details, add the callouts, those types of things in order for our 2D deliverable. And then we have a shop drawing review time. This isn't an internal review time. It's review time for our design team. Oftentimes, you have a spec that says that shop drawings have to be submitted as a deferred submittal. That time needs to be accounted for because even though you could potentially start, let's say doing hangars during that review time, something might come back that you didn't account for, or that we need to go back and change again. So you do you do want to account for it.

And then we have this material fab and procure. Particularly if you are not chasing pour dates, for instance, and you're chasing a rough install date, you do need to have time to fab your stuff or to procure your equipment so that it can actually get to the job site and be installed when the rough install date does show up.

So the coordination process is the next step. But real fast, I almost forgot to jump back into Excel to add in those dates because this becomes important later on down the line. So we had our three activities here. We need days to generate them. Let's say we're going to give people seven days because they've already built their spine. Spec says we have to give three weeks to our design team in order to review those. It's 21 calendar days. And then the fab and procure time. If we're leaving out any outliers of long lead items and that kind of a thing, we're probably going to do that in about a two week period of time per floor. So we end up with 14 calendar days in there.

So now when we come back into our coordination process being the next step, we've split these out into-- we have our initial model upload, our BIM coordination time, and then also our model sign off. And what these are is that the initial upload is that, even though you might have uploaded stuff to your FTP site, Box, BIM 360, Glue, whatever the case might be, this is the day that 100% or really close to 100% of that modeled content from your trade contractor has been uploaded to Glue. That's your drop dead date.

The next one here is the coordination. This is the only time in the schedule when we've allotted for clash rounds. This is the time that we have in order to be able to do clash detection, look at the clashes, resolve the clashes, and do that part that we most associate with the BIM coordination.

Then we have model sign off. Sadly, model sign off has one of two forms. It can be either clash free, or it can be that our schedule says we need to move on. More often than not, it's that we need to move on. So that model sign off date is just there to say, "This is the milestone that we have to work towards. Let's get clash free by this date. And if we can't, then we need to have some kind of discussion as to what happened." Or it could be that we've just reduced our clashes to an acceptable amount, and the rest can be taken care of in the field.

So let's jump back into Excel. I know there's a lot of jumping back and forth here in order to build this out. But with the formulas here, all we need to do is put in our time that we're going to spend actually doing clashes. And let's say that this can be done relatively quickly, meaning that we have maybe a weekly meeting, we're doing the first meeting, we have a meeting in between, and then we have a sign off meeting. So with weeklies, that means that we're going to take three weeks, so it's 21 calendar days.

All right, next part in here is content modeling. Now content modeling, a lot of times, it's what content are we going to use. If we're using the design team's model, then we need to wait for the design team to have that content ready for us to coordinate. That probably isn't going to happen until, at a minimum, 100% DDs. Leading up through schematic design, you probably don't have enough content in there. And so we need to wait for it.

If the trades are going to be doing it, we need to have which trades are going to be providing models, already on board and engaged, and make sure that they have time to generate their own content because what inevitably happens is that we get a superintendent, he's like, OK, we've got our electrician on board. They're ready to go tomorrow, and that's just not the case.

Electrical engineers are great, but they don't model in all of the small conduits. We require our electricians to model in all those small conduits. So they need time to actually model it. Otherwise, we can't coordinate it. We can't clash it. And we're just going to talk in a bunch of what ifs, and it's not going to be very productive. We need to allot some time in there to do that.

Also, when we have specialty trades, like P tube and that kind of thing, they need time to generate their own content. Whether we're doing that in the design process or whether we're doing it in construction coordination, we need some time to be able to generate this content.

So in our scenario, we're going to assume, just for the intent of the class, that our trades are going to be doing it. We're going to give them two weeks in order to be able to do that. And I just dropped my mouse. So that's awesome. All right, so 14 calendar days, there we go.

All right, then we have equipment submittals. Now equipments submittals, it's odd that we've placed this before everything. But the whole thing happens in a sequence. We need equipment in order-- or at least that submittal before we can make the content modeling because if we have to model to LOD 400, we have to know what we're modeling.

We can't just say, "Yeah, it's a VAV unit." OK, which VAV unit? Is it Siemens? Is it LG? Is it GE?

Whatever the case might be, same thing happens with the VRFs and those kinds of things. There's lots of different companies that make them. We need to know what we're going to model. And then we need to know what equipment we need.

Now the whole thing is that I would argue, we need everything. But there are some things that are probably higher priorities then, and some things that are lower priorities. A two by four troffer light has a certain amount of clearance that every single troffer light, regardless of manufacturer, is going to need in order to be able to install the light and repair the light and that kind of thing. So we can let those things slide a little bit.

But air handlers, you need to know what air handler you're putting in. If you don't know, then you're just talking in another what if scenario because you don't really know. You don't have that information in there.

So and then owner provided equipment becomes very critical at this stage because our trades aren't providing it, but we need to know about it. So particularly in this case, we have an imaging suite. Chances are they're going to have an x-ray that is owner provided. That x-ray requires structure to go up above the ceiling.

Now it's whose job is it to provide that structure? Is it going to be the supplier, or is it going to be coming in from someone like Unistrut? And we're going to have the structure ready for them that they can connect any x-ray machine to. We need to have that discussion early.

So what we're going to assume here-- yeah, that's where I put it. As we jump back into Excel at least for right now, we're going to start assuming that all of our guys have been engaged for at least a week or so. They've started on their submittal process, and they really only need probably another two weeks in order to finish that out per floor.

So now we have some actual dates in here, and what is really fun to look at, now that we have some dates, is that if we were handed this project today and we needed to coordinate it chasing these January dates, we're not going to make it. And the reason is we should have started two months ago, back in September. That's when we should have been engaging our trade modelers. That's when we should have been starting this whole process.

Now all is not necessarily lost. At this point, we can come in and we can do probably something, but we're going to have to start negotiating some of these durations. Maybe we're going to leave out a stage or something like that. Maybe we're going to say, "You know what? They're going to install hangars even though it hasn't been through the review process." That saves us three weeks.

So we can start playing with the numbers here. So we get rid of that review process time, and now we're getting into October. So or maybe we just say, "You know what? We're good enough with whatever the design team's given us. We're not going to worry about doing the submittal process." And now we're getting closer to our actual dates that we're at right now.

So this process becomes very important because now we have a conversation starter. Now we have actual firm dates that we can go back to our project team, or our owner, or architect, or whoever is the one that we need to sell our schedule to, as to when we need to get started and show them, look, if I need to beat this date, I need this amount of time, and we need to start next week, for instance. So this becomes a very powerful planning tool, and then we keep it up to date throughout the process. And we'll talk through that.

All right, so our schedule detail when we jump into this, we need to have enough detail that we're showing everything basically. But, in here, we are grouping all of our MEP subcontractors, all of our steel, all of our specialty trades into one single activity. And that's what we've done thus far, which goes against a little bit of what standard scheduling practice would necessarily be. And that's because BIM is really an all for nothing, or all for one workflow. If your plumber starts to fall behind, it hurts everyone.

Now that doesn't mean that we can't do phased work. We can do phased work. It's just that you have to plan for that appropriately. And if you don't plan for it appropriately, things start to get muddy. So with phased work, we would add additional activities, maybe we would say instead of grouping all of level one, we'd have level one plumbing. And we would know that hey, it's going to be seven days into the coordination process before our sheet metal guy is engaged and has a model uploaded to the BIM 360 Glue site or whatever case might be.

And this is where Excel and Plan start to differentiate themselves because Plan, you can just add in those specific activities, and you don't have to worry about adding additional lines to your Excel spreadsheet, becomes a little bit easier to manage that logic. We do need to add project specific activities to our schedule. No two projects are the same. We break it down pretty good for the process here that process is pretty repeatable, but no two projects are the same. You're going to have stuff that is a little bit different.

Then you need to get on your master schedule. So even though you as the BIM lead, you might not have access to P6, or you might not know P6, but your company uses P6 in order to do the master schedule, but your master schedule is what you order. When you go into sub meeting, that's what they're looking at. At OEC, that's what they're looking at.

So you want to be on the schedule that they're looking at. Otherwise, you will get lost, you will get left behind, and then it turns into a little bit of a cluster later on down in the process when you think you're humming along just fine. But they sped up the pour dates by a week, and you didn't know about it. But having your stuff in the master schedule will prompt your scheduler to come and talk to you and say, "Hey, we affected your dates. We need to talk about this, and what we can do for a plan."

So which leads us right into collaborating with stakeholders. Now we do have another funny Dilbert video here.

[VIDEO PLAYBACK]

- Sales are dropping like a rock. Our plan is to invent some sort of do hickey that everyone wants to buy. Ah, well, the visionary leadership work is done. How long will your part take?

[BELL RINGING]

[END PLAYBACK]

[VIDEO PLAYBACK]

[MUSIC PLAYING]

- I need you to facilitate some meetings.

- What kind of meetings?

- We're creating a process to fix our product development process. But first, we're having some preplanning meetings to decide on a project name.

- How about death spiral?

[END PLAYBACK]

NICK DYER: [LAUGHS] OK, everyone hates the whole thing of let's have a meeting to plan the next meeting. I know everyone hates them. I hate them, but sometimes, they actually do have some importance.

So we have our pre-kickoff meetings. So in this scenario, we've gone through that Excel spreadsheet or we've gone through Plan, we've added our activities, we've added durations. But we haven't talked to anyone yet.

So we do need to do that exercise on our own in order to account for planning, but then we need to have a pre-kickoff meeting. And this is one on one with each of your individual trades. It can be over the phone, and it needs to be really quick. 30 minutes is usually sufficient. I can pretty much get through my agenda in about 30 minutes. So these are not meant to be long, lingering meetings.

Basically, we're going to be talking proposed schedule. We're going to be talking submittals. And we're going to be talking our RFIs.

Now if they've been engaged for a while, they're going to have some of all of this complete. So with the proposed schedule, we need to make sure that they're on board, that we've got a consensus, that the durations and dates that we have provided, that they actually feel like they can hit. If we haven't talked to them, it's like that Dilbert cartoon where he goes, "Hey, I've done my part. How long is it going to take to do your part?". We don't know because we haven't talked to him yet. That's the point of this meeting.

The other one is that we need to make sure that our submittals are complete. And then what long leads we might have because if we have a long lead item, we need to get that submittal in now basically. And we all know that, and your project team is probably going to help you through that process anyway because it's so important that long leads get taken care of early. But a lot of times with long lead items, we can go to the manufacturer for let's say, our heat pumps or something like that, and we can get those cut sheets early and get them into the model before the submittal is necessarily approved. We just need to make that decision.

Then with RFIs, chances are, during the bidding process, they've already submitted some RFIs, but did they get RFI responses that were complete? I always hate it when they only answer 70% of the question, or you ask two questions, and they only answer one. Sometimes it happens, though. We just need to make sure that anything that needs to be submitted is already into the system. RFIs are our enemy during the BIM coordination process, and I'm sure most of you are already aware of that.

So next introduction here.

[VIDEO PLAYBACK]

[MUSIC PLAYING]

- I desperately need to take this training.

- We can't spare you. Send Wally and have him tell you what he learned.

- I'm awed by the shear artistry of your mismanagement skills.

- Thank you.

[BELL RINGING]

[END PLAYBACK]

NICK DYER: Yeah, so the whole thing is that with the kickoff meeting, you need to get people there in person, and you need to have everyone, the more, the merrier. I hate it when the subcontractors will bring to the meeting, and they will bring their project manager, and that's it. And it's like, dude, it's a BIM coordination kickoff. We need your modeler, and we need your foreman. Those are your guys that are probably we're going to be talking to more often than the project manager for the trade.

So we need those people, and we need them in person. Another reason for having them in person is that a lot of times, we do the telecommunicating where it's Go To Meeting, or Zoom, or one of those other services. And so we need to make sure that people see each other face to face because we're going to clash, we're going to have conflict. And the thing is, is that you're more willing to say mean things to somebody you don't know than to people you do know. So by having that, you tend to have a more civil conflict resolution process.

So again, we have an agenda. We have our proposed schedule, our submittals, and our RFIs. Now this is it in addition to whatever else you might have on your agenda for your BIM kickoff meeting. But we're going to hit these big three again.

Here, since we've talked to everyone, no one should be surprised by the coordination schedule at this point. Everyone should be on board with the durations, dates. We know where we're headed. It's just a reiteration of what's going on.

Then here, we are going to look at what's complete, what's our long lead items with submittals, what's important because sometimes, what'll happen is is that something that's not necessarily important to the sheet metal guy is really important to the electrician. And it might be the sheet metal guy's submittal that they need to get pushed through. So we need to make sure that submittals are getting pushed, and that we've got the right priorities.

And then again, we need to hit on RFIs. In this case, we're going to talk about open RFIs because, at this stage, we should have gotten all of the answers back. But if we have any open ones, we want to make sure to talk about them, especially since what happens is the domino effect.

I just had a problem on my current project that I'm working on where we moved some duct, the duct moved steel. Luckily, it was steel that was just field welded into place, a couple of brace angles and that kind of thing. It was really easy to move, but because of that duct move, it affected the steel. And the steel contractor wouldn't have known about it if we had not talked about it in the coordination meeting because our structural guy did not issue new drawings for the steel change, because it was a duct change. So it happens.

Then we have the coordination meeting. Now the coordination meeting, in addition to clashes and however else you do your coordination meetings, isn't really important, but I do these things first. We talk about schedule. We talk about where we are. Here's where we're at today. We should be working on shop drawings for level two. We're in the middle of coordination on the penthouse, and we should have been fabbing all of our stuff for level one.

You had a lot of activities going on at that point. You need to make sure that everyone's aware of what activities should be going on. And if there's some kind of roadblock, this is the time to talk about it.

Again, we're going to hit on submittals. But it's this never ending train of submitters at this point. And the same thing goes for RFIs, so--

[VIDEO PLAYBACK]

[MUSIC PLAYING]

- My project has no progress and no hope for progress. I scheduled a meeting so I can fantasize that it will produce a breakthrough. I recommend that we have a meeting next week so you can fantasize that you'll coach me to higher levels of performance.

- Sounds good.

[BELL RINGING]

[END PLAYBACK]

NICK DYER: So meetings are actually important. If they're not going to be productive, don't have them because then it's just a fantasy. So we do need to hit on these things in order to be able to hold our stakeholders accountable. So we have, I promise, one last video to introduce assumptions here when it comes to transparency.

[VIDEO PLAYBACK]

[MUSIC PLAYING]

- I need help making unrealistic assumptions to support a business case for a bad idea.

- Easy. There's a hole in the back of our wardrobe closet that leads to a magical world of preposterous business assumptions.

- We don't have a wardrobe closet.

- Assume we do.

[BELL RINGING]

[END PLAYBACK]

NICK DYER: OK, so assumptions, you know the old saying they make an ass out of you and me? So the reason for that is that if we start assuming that everyone is trucking along, and that they're doing what they've been told to do, and we aren't verifying that people are doing that and holding them accountable, it turns into a giant assumption. We're going to assume that they knew what to do. We're going to assume that they're on track. We need to have that check.

So accountability and transparency, they start to sound like the same thing, and the reason is is that they are very interconnected with each other. Now with this, because we've had a schedule, because the trades have had input on that schedule, we can ensure that they know what the schedule is. But we review it in every single meeting because it's really important to note that they're on track. We need to double check and just make sure that everything is going well.

When it comes to transparency, because we've reviewed the schedule again in every single meeting, everyone knows where everyone should be. No one is questioning why if we have phase work, for instance. No one's questioning why fire protection hasn't uploaded their model yet. They know that, in the schedule, that they might not be uploading that until a week after we've started coordination.

We might be phasing in the work if that's the case or something around that. And then I always hate it when the coordination meeting is brought to a halt because the duct guy is curious because there's a whole bunch of clashes in there that's not even his scope, not even something that he should be paying attention to, but there's a whole bunch of clashes assigned to the electrician that haven't been cleared up. And it's because the electrician is on a different schedule than our duct guy.

It happens when we phase the work like that. And having a schedule brings forth that transparency so we know where each other are. It also lets people know that, at a certain stage, if we've signed off duct, they're not going to move. We need to move around them. And the cycle continues

And then we have the example here that you have a subcontractor falling behind for the second week in a row. That subcontractor knows that they're falling behind. We don't assume that they know that they're falling behind. At this point, they know it. And it allows them the opportunity to say, "You know what? We're putting two more guys on it in order to catch ourselves up."

So we're going to talk about incorporating a roadblock or a delay. This seems like a pretty outlandish hypothetical scenario. But I actually have encountered a scenario similar to this where we've placed a bathroom group above an electrical room. Now sometimes this happens, and we install drip pans, and everything's great.

But in this case, our owner came back and said, "Nope, no plumbing over the electrical room period." Now we have a problem because the design team has to either redesign the electrical room, or they need to redesign the bathroom group up above. So this does need to be accounted for, and it needs to be accounted for through a handshake. And the answer to that would be a solid no.

And it needs to be accounted for in meeting minutes. And that is true, but probably should be accounted for in other places. And the answer is that it needs to be accounted for in our schedule. If we don't account for it in the schedule, then we aren't looking at it when we go to our schedule update meetings, and then we've lost our transparency.

So we're going to say that our baseline had gave us 21 days in our schedule. The RFI's response was received on day nine. And then the design team wants 21 days in order to redesign this. And we need another seven days to incorporate it and catch up to where we were in our coordination effort.

Now this doesn't mean that we're not coordinating the building in other spaces, but what it does mean is that this particular area of effect is on hold. So because we don't know what's going to happen, it's not worth our time. It's not responsible to keep moving forward.

So we get our 21 days. We have nine days in the coordination. We add our 21 days of design, and then our seven days for the trades. And we end up with 40 days total.

But we take our 21 day baseline, and we subtract that from the 40 days. And we end up with a 19 day delay. So we've minimized the amount of delay that we're going to experience on this because we're going to assume that this is the only area that's going to be affected by that 19 days. And I know I just said the word assume, but sometimes, we have to.

So we're going to coordinate the other areas. We started off. We're in day nine, so we're well into our coordination process. We're going to coordinate in the other spaces. It's only this area that's been affected that we're going to pause.

And so when we come back after the 21 days from our design team, we have seven days to coordinate this area and get back on track. So we've minimized a 40 day delay down to a 19 day delay. We've cut that in half by leveraging our schedule and continuing to move forward.

All right, so with RFIs, small RFIs that only cause maybe two days of effect, they're probably not going to affect our schedule. In fact, we should just plan on them in our duration. If everything went perfect, we could probably finish buildings a whole lot faster.

But what ends up happening is that you end up with 12 small RFIs that all take two days apiece, and now we're up to 24 days instead of 21 days. So these things have to be accounted for. So even if an RFI is only going to take two days, you need to account for it in your schedule because if you don't, then, all of a sudden, when you're only three days behind, everyone's going, wait a second, you Said you'd be done three days ago. What happened?

And this gives you the ability to go back and be like, well, we had RFI 256, and 300, and 302, and 319, and 400, and so on down the line. And then it adds a lot of paper trail to that.

Then you have a drop dead date. Now this is something that because I'm on the contractor side of things, basically I give my design team a drop dead date. I tell them, "Look, if you give me a response by 7:00 AM on this day, it won't affect our schedule." And oftentimes, I will get a response by that day because the design team does not want to be held accountable for delaying our BIM, especially nowadays when owners are starting to watch what we're doing.

So in terms of implementing these scheduling strategies, we need to get on the master schedule. That is, by far, the most important takeaway from this entire thing. If you are on the master schedule and it just says, "You have six weeks." You're really not on the master schedule. That six weeks does not encompass all of these different stages that we've just talked about. We need to have that breakdown however you broke it down on your schedule, that should be a mirror image of what is in the master schedule, and we need that into your master schedule.

Next thing is we need to review our historical data. So a big thing here is that, especially when Oakland started to do this, we had already been doing BIM coordination for about four years, and we had not really analyzed our historical data to that point. And we didn't realize that hey, when it came to an office, we were actually finishing a floor in an office space in about two weeks. But when it was a hospital, we were finishing that in four weeks. But we were always telling people it's three weeks, so we had that ability to then go back and say, "You know what? We can come up with better durations and tighten some things up."

All right, we had that dinosaur, and we were able to trim it into a much better dinosaur. So you need to insist on being part of your project scheduling meeting. Now I don't know if that happens at your sub meeting, or if you have a specific scheduling meeting, or if it happens in OAC, or if your superintendent just updates it on a weekly basis, but you need to insist on being part of it.

It really only takes five-ish, 10-ish minutes in order to update the schedule, especially when you're doing it every single week. It's worth your time because when it comes to the trade meeting, or the sub meeting, or the OAC meeting, and they don't have your current information, they are going to think that everything's trucking along just fine, even though maybe yesterday in your coordination meeting, you came across a really big issue that's going to cause a 19 day delay. And now in OAC, we have egg on our face because we didn't tell him about that last week.

And then if you have a scheduling department, train your scheduling department, or train whoever is in charge of training your schedulers. At Oakland Construction, we actually have a corporate scheduling department. But then our superintendents are in charge of maintaining that schedule after construction begins.

So essentially, there's a handoff. Sometimes their scheduling department stays involved, sometimes they don't. But the point is that if you have a training meeting, and what I did is I just gave them this. And I know you have to strain your eyes a little bit to see it, but it's just a whole bunch of activities with saying, "Hey, you know what? It's getting to this part. It's going to take two to four weeks. This part takes two to three weeks."

And then it just-- you can take that pattern and just repeat it over and over for every floor that you have. This allows us that if all else fails, and they haven't come and talk to you yet, we get something that looks like a breakdown that we can actually use. And we don't end up with six weeks for BIM. We end up with an appropriate amount of detail.

And then it's really easy that if we need to extend one of these activities or shorten one up or something like that, we actually have an activity to relate that to. And also, whoever is reading this schedule in the early stages, they're seeing it as like, oh, man, BIM is this whole big process instead of BIM is six weeks.

So to summarize, we're going to create our schedule. I know we didn't touch a whole lot in BIM 360 Plan, but we covered a little bit of the basics. We can add our durations. We can add our stuff, our logic to that schedule as well. And we also looked at an Excel spreadsheet that we can use.

So we also looked at how to collaborate with our stakeholders. Basically, we're having another meeting. I know it stinks, but a 30 minute conversation is way better than having a fight in your kickoff meeting over dates, especially when you've locked them in.

And then we're going to hold them accountable by reviewing that schedule repeatedly. We're going to make sure that everyone knows where we're at with our schedule. And then with strategies, what's important here is get on your master schedule. Everything else is to support better ways of getting onto the master schedule. And you have to start somewhere, and it doesn't really matter where you start. Starting now is better than starting a year from now.

And with that, we'll open it up to questions. I can re-go back into the spreadsheet or Plan if people want to, but we'll move into this part of the presentation. Any questions from the group? All right, not seeing any hands, but, in that case, I appreciate you guys coming and coming to my session and listening to me ramble on and-- oh, hey, question. All right.

AUDIENCE: [INAUDIBLE]

NICK DYER: All right, cool. All right, in that case-- oh, hey, yes?

AUDIENCE: So do you work for [INAUDIBLE] contractor or [INAUDIBLE]?

NICK DYER: So we do everything. We do design, build. We even have some integrated project delivery projects going on right now. And we have two prefabricated projects going on right now, too. So we run the whole gambit, basically.

We don't limit ourselves to any one kind of construction. But the vast majority of our projects are still CMGC or design assist. Those are the two most common contracts we end up picking up.

AUDIENCE: [INAUDIBLE]

NICK DYER: Yeah, exactly.

AUDIENCE: [INAUDIBLE]

NICK DYER: Exactly. Yeah.

AUDIENCE: [INAUDIBLE]

NICK DYER: Yeah. Yes, it cuts down the schedule dramatically when we're in that because yeah, just like you're saying, in-house engineering team, you don't have RFIs, maybe you have issues, but you can track issues a whole lot faster than you can track RFIs. So yeah, it becomes a lot quicker, so--

AUDIENCE: [INAUDIBLE]

NICK DYER: OK.

AUDIENCE: [INAUDIBLE] You just said the exact same thing. [INAUDIBLE]

NICK DYER: Yeah, I totally agree.

AUDIENCE: [INAUDIBLE]

NICK DYER: Thank you.

AUDIENCE: [INAUDIBLE]

NICK DYER: So because our trades are contracted to our master schedule, and this ends up in the master schedule, that's how we hold them accountable on the contract. But it is also part of our-- it's like an addendum to our BIM execution plan, and our BIM execution plan is also contractual. So there's a lot of different angles to attack it.

AUDIENCE: [INAUDIBLE]

NICK DYER: So I use BIM 360 Plan only to keep my own personal schedule because Oakland requires all of our BIM leads to have their own personal schedule. But then we take that and we export it out to an-- because you can export to XML, and then we take that XML and put it into our P6. And then because they can attach then that separated P6 into the master schedule, it becomes a really easy way to communicate back and forth. But also, in addition to the sharing of that file, we also have to talk to each other because sometimes they just don't notice that the dates changed. So all right, any other questions? Well, I thank you for coming and listening to me ramble and--

[APPLAUSE]

Thank you.

______
icon-svg-close-thick

쿠기 기본 설정

오토데스크는 고객의 개인 정보와 최상의 경험을 중요시합니다. 오토데스크는 정보를 사용자화하고 응용프로그램을 만들기 위해 고객의 본 사이트 사용에 관한 데이터를 수집합니다.

오토데스크에서 고객의 데이터를 수집하고 사용하도록 허용하시겠습니까?

오토데스크에서 사용하는타사 서비스개인정보 처리방침 정책을 자세히 알아보십시오.

반드시 필요 - 사이트가 제대로 작동하고 사용자에게 서비스를 원활하게 제공하기 위해 필수적임

이 쿠키는 오토데스크에서 사용자 기본 설정 또는 로그인 정보를 저장하거나, 사용자 요청에 응답하거나, 장바구니의 품목을 처리하기 위해 필요합니다.

사용자 경험 향상 – 사용자와 관련된 항목을 표시할 수 있게 해 줌

이 쿠키는 오토데스크가 보다 향상된 기능을 제공하고 사용자에게 맞는 정보를 제공할 수 있게 해 줍니다. 사용자에게 맞는 정보 및 환경을 제공하기 위해 오토데스크 또는 서비스를 제공하는 협력업체에서 이 쿠키를 설정할 수 있습니다. 이 쿠키를 허용하지 않을 경우 이러한 서비스 중 일부 또는 전체를 이용하지 못하게 될 수 있습니다.

광고 수신 설정 – 사용자에게 타겟팅된 광고를 제공할 수 있게 해 줌

이 쿠키는 사용자와 관련성이 높은 광고를 표시하고 그 효과를 추적하기 위해 사용자 활동 및 관심 사항에 대한 데이터를 수집합니다. 이렇게 데이터를 수집함으로써 사용자의 관심 사항에 더 적합한 광고를 표시할 수 있습니다. 이 쿠키를 허용하지 않을 경우 관심 분야에 해당되지 않는 광고가 표시될 수 있습니다.

icon-svg-close-thick

타사 서비스

각 범주에서 오토데스크가 사용하는 타사 서비스와 온라인에서 고객으로부터 수집하는 데이터를 사용하는 방식에 대해 자세히 알아보십시오.

icon-svg-hide-thick

icon-svg-show-thick

반드시 필요 - 사이트가 제대로 작동하고 사용자에게 서비스를 원활하게 제공하기 위해 필수적임

Qualtrics
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 Qualtrics를 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. 오토데스크는 이 데이터를 다른 소스에서 수집된 데이터와 결합하여 고객의 판매 또는 고객 서비스 경험을 개선하며, 고급 분석 처리에 기초하여 보다 관련 있는 컨텐츠를 제공합니다. Qualtrics 개인정보취급방침
Akamai mPulse
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Akamai mPulse를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Akamai mPulse 개인정보취급방침
Digital River
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Digital River를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Digital River 개인정보취급방침
Dynatrace
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Dynatrace를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Dynatrace 개인정보취급방침
Khoros
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Khoros를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Khoros 개인정보취급방침
Launch Darkly
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Launch Darkly를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Launch Darkly 개인정보취급방침
New Relic
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 New Relic를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. New Relic 개인정보취급방침
Salesforce Live Agent
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Salesforce Live Agent를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Salesforce Live Agent 개인정보취급방침
Wistia
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Wistia를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Wistia 개인정보취급방침
Tealium
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Tealium를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Upsellit
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Upsellit를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. CJ Affiliates
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 CJ Affiliates를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Commission Factory
Typepad Stats
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Typepad Stats를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Typepad Stats 개인정보취급방침
Geo Targetly
Autodesk는 Geo Targetly를 사용하여 웹 사이트 방문자를 가장 적합한 웹 페이지로 안내하거나 위치를 기반으로 맞춤형 콘텐츠를 제공합니다. Geo Targetly는 웹 사이트 방문자의 IP 주소를 사용하여 방문자 장치의 대략적인 위치를 파악합니다. 이렇게 하면 방문자가 (대부분의 경우) 현지 언어로 된 콘텐츠를 볼 수 있습니다.Geo Targetly 개인정보취급방침
SpeedCurve
Autodesk에서는 SpeedCurve를 사용하여 웹 페이지 로드 시간과 이미지, 스크립트, 텍스트 등의 후속 요소 응답성을 측정하여 웹 사이트 환경의 성능을 모니터링하고 측정합니다. SpeedCurve 개인정보취급방침
Qualified
Qualified is the Autodesk Live Chat agent platform. This platform provides services to allow our customers to communicate in real-time with Autodesk support. We may collect unique ID for specific browser sessions during a chat. Qualified Privacy Policy

icon-svg-hide-thick

icon-svg-show-thick

사용자 경험 향상 – 사용자와 관련된 항목을 표시할 수 있게 해 줌

Google Optimize
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Google Optimize을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Google Optimize 개인정보취급방침
ClickTale
오토데스크는 고객이 사이트에서 겪을 수 있는 어려움을 더 잘 파악하기 위해 ClickTale을 이용합니다. 페이지의 모든 요소를 포함해 고객이 오토데스크 사이트와 상호 작용하는 방식을 이해하기 위해 세션 녹화를 사용합니다. 개인적으로 식별 가능한 정보는 가려지며 수집되지 않습니다. ClickTale 개인정보취급방침
OneSignal
오토데스크는 OneSignal가 지원하는 사이트에 디지털 광고를 배포하기 위해 OneSignal를 이용합니다. 광고는 OneSignal 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 OneSignal에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 OneSignal에 제공하는 데이터를 사용합니다. OneSignal 개인정보취급방침
Optimizely
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Optimizely을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Optimizely 개인정보취급방침
Amplitude
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Amplitude을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Amplitude 개인정보취급방침
Snowplow
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Snowplow를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Snowplow 개인정보취급방침
UserVoice
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 UserVoice를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. UserVoice 개인정보취급방침
Clearbit
Clearbit를 사용하면 실시간 데이터 보강 기능을 통해 고객에게 개인화되고 관련 있는 환경을 제공할 수 있습니다. Autodesk가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. Clearbit 개인정보취급방침
YouTube
YouTube는 사용자가 웹 사이트에 포함된 비디오를 보고 공유할 수 있도록 해주는 비디오 공유 플랫폼입니다. YouTube는 비디오 성능에 대한 시청 지표를 제공합니다. YouTube 개인정보보호 정책

icon-svg-hide-thick

icon-svg-show-thick

광고 수신 설정 – 사용자에게 타겟팅된 광고를 제공할 수 있게 해 줌

Adobe Analytics
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Adobe Analytics를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID 및 오토데스크 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. Adobe Analytics 개인정보취급방침
Google Analytics (Web Analytics)
오토데스크 사이트에서 고객의 행동에 관한 데이터를 수집하기 위해 Google Analytics (Web Analytics)를 이용합니다. 여기에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 오토데스크는 사이트 성과를 측정하고 고객의 온라인 경험의 편리함을 평가하여 기능을 개선하기 위해 이러한 데이터를 이용합니다. 또한, 이메일, 고객 지원 및 판매와 관련된 고객 경험을 최적화하기 위해 고급 분석 방법도 사용하고 있습니다. AdWords
Marketo
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 Marketo를 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. 오토데스크는 이 데이터를 다른 소스에서 수집된 데이터와 결합하여 고객의 판매 또는 고객 서비스 경험을 개선하며, 고급 분석 처리에 기초하여 보다 관련 있는 컨텐츠를 제공합니다. Marketo 개인정보취급방침
Doubleclick
오토데스크는 Doubleclick가 지원하는 사이트에 디지털 광고를 배포하기 위해 Doubleclick를 이용합니다. 광고는 Doubleclick 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Doubleclick에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Doubleclick에 제공하는 데이터를 사용합니다. Doubleclick 개인정보취급방침
HubSpot
오토데스크는 고객에게 더욱 시의적절하며 관련 있는 이메일 컨텐츠를 제공하기 위해 HubSpot을 이용합니다. 이를 위해, 고객의 온라인 행동 및 오토데스크에서 전송하는 이메일과의 상호 작용에 관한 데이터를 수집합니다. 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 이메일 확인율, 클릭한 링크 등이 포함될 수 있습니다. HubSpot 개인정보취급방침
Twitter
오토데스크는 Twitter가 지원하는 사이트에 디지털 광고를 배포하기 위해 Twitter를 이용합니다. 광고는 Twitter 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Twitter에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Twitter에 제공하는 데이터를 사용합니다. Twitter 개인정보취급방침
Facebook
오토데스크는 Facebook가 지원하는 사이트에 디지털 광고를 배포하기 위해 Facebook를 이용합니다. 광고는 Facebook 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Facebook에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Facebook에 제공하는 데이터를 사용합니다. Facebook 개인정보취급방침
LinkedIn
오토데스크는 LinkedIn가 지원하는 사이트에 디지털 광고를 배포하기 위해 LinkedIn를 이용합니다. 광고는 LinkedIn 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 LinkedIn에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 LinkedIn에 제공하는 데이터를 사용합니다. LinkedIn 개인정보취급방침
Yahoo! Japan
오토데스크는 Yahoo! Japan가 지원하는 사이트에 디지털 광고를 배포하기 위해 Yahoo! Japan를 이용합니다. 광고는 Yahoo! Japan 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Yahoo! Japan에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Yahoo! Japan에 제공하는 데이터를 사용합니다. Yahoo! Japan 개인정보취급방침
Naver
오토데스크는 Naver가 지원하는 사이트에 디지털 광고를 배포하기 위해 Naver를 이용합니다. 광고는 Naver 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Naver에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Naver에 제공하는 데이터를 사용합니다. Naver 개인정보취급방침
Quantcast
오토데스크는 Quantcast가 지원하는 사이트에 디지털 광고를 배포하기 위해 Quantcast를 이용합니다. 광고는 Quantcast 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Quantcast에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Quantcast에 제공하는 데이터를 사용합니다. Quantcast 개인정보취급방침
Call Tracking
오토데스크는 캠페인을 위해 사용자화된 전화번호를 제공하기 위하여 Call Tracking을 이용합니다. 그렇게 하면 고객이 오토데스크 담당자에게 더욱 빠르게 액세스할 수 있으며, 오토데스크의 성과를 더욱 정확하게 평가하는 데 도움이 됩니다. 제공된 전화번호를 기준으로 사이트에서 고객 행동에 관한 데이터를 수집할 수도 있습니다. Call Tracking 개인정보취급방침
Wunderkind
오토데스크는 Wunderkind가 지원하는 사이트에 디지털 광고를 배포하기 위해 Wunderkind를 이용합니다. 광고는 Wunderkind 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Wunderkind에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Wunderkind에 제공하는 데이터를 사용합니다. Wunderkind 개인정보취급방침
ADC Media
오토데스크는 ADC Media가 지원하는 사이트에 디지털 광고를 배포하기 위해 ADC Media를 이용합니다. 광고는 ADC Media 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 ADC Media에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 ADC Media에 제공하는 데이터를 사용합니다. ADC Media 개인정보취급방침
AgrantSEM
오토데스크는 AgrantSEM가 지원하는 사이트에 디지털 광고를 배포하기 위해 AgrantSEM를 이용합니다. 광고는 AgrantSEM 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 AgrantSEM에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 AgrantSEM에 제공하는 데이터를 사용합니다. AgrantSEM 개인정보취급방침
Bidtellect
오토데스크는 Bidtellect가 지원하는 사이트에 디지털 광고를 배포하기 위해 Bidtellect를 이용합니다. 광고는 Bidtellect 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Bidtellect에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Bidtellect에 제공하는 데이터를 사용합니다. Bidtellect 개인정보취급방침
Bing
오토데스크는 Bing가 지원하는 사이트에 디지털 광고를 배포하기 위해 Bing를 이용합니다. 광고는 Bing 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Bing에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Bing에 제공하는 데이터를 사용합니다. Bing 개인정보취급방침
G2Crowd
오토데스크는 G2Crowd가 지원하는 사이트에 디지털 광고를 배포하기 위해 G2Crowd를 이용합니다. 광고는 G2Crowd 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 G2Crowd에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 G2Crowd에 제공하는 데이터를 사용합니다. G2Crowd 개인정보취급방침
NMPI Display
오토데스크는 NMPI Display가 지원하는 사이트에 디지털 광고를 배포하기 위해 NMPI Display를 이용합니다. 광고는 NMPI Display 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 NMPI Display에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 NMPI Display에 제공하는 데이터를 사용합니다. NMPI Display 개인정보취급방침
VK
오토데스크는 VK가 지원하는 사이트에 디지털 광고를 배포하기 위해 VK를 이용합니다. 광고는 VK 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 VK에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 VK에 제공하는 데이터를 사용합니다. VK 개인정보취급방침
Adobe Target
오토데스크는 사이트의 새 기능을 테스트하고 이러한 기능의 고객 경험을 사용자화하기 위해 Adobe Target을 이용합니다. 이를 위해, 고객이 사이트를 방문해 있는 동안 행동 데이터를 수집합니다. 이 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역, IP 주소 또는 장치 ID, 오토데스크 ID 등이 포함될 수 있습니다. 고객은 기능 테스트를 바탕으로 여러 버전의 오토데스크 사이트를 경험하거나 방문자 특성을 바탕으로 개인화된 컨텐츠를 보게 될 수 있습니다. Adobe Target 개인정보취급방침
Google Analytics (Advertising)
오토데스크는 Google Analytics (Advertising)가 지원하는 사이트에 디지털 광고를 배포하기 위해 Google Analytics (Advertising)를 이용합니다. 광고는 Google Analytics (Advertising) 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Google Analytics (Advertising)에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Google Analytics (Advertising)에 제공하는 데이터를 사용합니다. Google Analytics (Advertising) 개인정보취급방침
Trendkite
오토데스크는 Trendkite가 지원하는 사이트에 디지털 광고를 배포하기 위해 Trendkite를 이용합니다. 광고는 Trendkite 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Trendkite에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Trendkite에 제공하는 데이터를 사용합니다. Trendkite 개인정보취급방침
Hotjar
오토데스크는 Hotjar가 지원하는 사이트에 디지털 광고를 배포하기 위해 Hotjar를 이용합니다. 광고는 Hotjar 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Hotjar에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Hotjar에 제공하는 데이터를 사용합니다. Hotjar 개인정보취급방침
6 Sense
오토데스크는 6 Sense가 지원하는 사이트에 디지털 광고를 배포하기 위해 6 Sense를 이용합니다. 광고는 6 Sense 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 6 Sense에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 6 Sense에 제공하는 데이터를 사용합니다. 6 Sense 개인정보취급방침
Terminus
오토데스크는 Terminus가 지원하는 사이트에 디지털 광고를 배포하기 위해 Terminus를 이용합니다. 광고는 Terminus 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 Terminus에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 Terminus에 제공하는 데이터를 사용합니다. Terminus 개인정보취급방침
StackAdapt
오토데스크는 StackAdapt가 지원하는 사이트에 디지털 광고를 배포하기 위해 StackAdapt를 이용합니다. 광고는 StackAdapt 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 StackAdapt에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 StackAdapt에 제공하는 데이터를 사용합니다. StackAdapt 개인정보취급방침
The Trade Desk
오토데스크는 The Trade Desk가 지원하는 사이트에 디지털 광고를 배포하기 위해 The Trade Desk를 이용합니다. 광고는 The Trade Desk 데이터와 고객이 사이트를 방문하는 동안 오토데스크가 수집하는 행동 데이터 모두에 기초하여 제공됩니다. 오토데스크가 수집하는 데이터에는 고객이 방문한 페이지, 시작한 체험판, 재생한 동영상, 구매 내역 및 IP 주소 또는 장치 ID가 포함될 수 있습니다. 이 정보는 The Trade Desk에서 고객으로부터 수집한 데이터와 결합될 수 있습니다. 오토데스크는 디지털 광고 경험에 대한 사용자화를 개선하고 고객에게 더욱 관련 있는 광고를 제시하기 위해 The Trade Desk에 제공하는 데이터를 사용합니다. The Trade Desk 개인정보취급방침
RollWorks
We use RollWorks to deploy digital advertising on sites supported by RollWorks. Ads are based on both RollWorks data and behavioral data that we collect while you’re on our sites. The data we collect may include pages you’ve visited, trials you’ve initiated, videos you’ve played, purchases you’ve made, and your IP address or device ID. This information may be combined with data that RollWorks has collected from you. We use the data that we provide to RollWorks to better customize your digital advertising experience and present you with more relevant ads. RollWorks Privacy Policy

정말 더 적은 온라인 경험을 원하십니까?

오토데스크는 고객 여러분에게 좋은 경험을 드리고 싶습니다. 이전 화면의 범주에 대해 "예"를 선택하셨다면 오토데스크는 고객을 위해 고객 경험을 사용자화하고 향상된 응용프로그램을 제작하기 위해 귀하의 데이터를 수집하고 사용합니다. 언제든지 개인정보 처리방침을 방문해 설정을 변경할 수 있습니다.

고객의 경험. 고객의 선택.

오토데스크는 고객의 개인 정보 보호를 중요시합니다. 오토데스크에서 수집하는 정보는 오토데스크 제품 사용 방법, 고객이 관심을 가질 만한 정보, 오토데스크에서 더욱 뜻깊은 경험을 제공하기 위한 개선 사항을 이해하는 데 도움이 됩니다.

오토데스크에서 고객님께 적합한 경험을 제공해 드리기 위해 고객님의 데이터를 수집하고 사용하도록 허용하시겠습니까?

선택할 수 있는 옵션을 자세히 알아보려면 이 사이트의 개인 정보 설정을 관리해 사용자화된 경험으로 어떤 이점을 얻을 수 있는지 살펴보거나 오토데스크 개인정보 처리방침 정책을 확인해 보십시오.