& Construction

Integrated BIM tools, including Revit, AutoCAD, and Civil 3D
& Manufacturing

Professional CAD/CAM tools built on Inventor and AutoCAD
Integrated BIM tools, including Revit, AutoCAD, and Civil 3D
Professional CAD/CAM tools built on Inventor and AutoCAD
Transcript
00:02
After completing this lesson,
00:03
you'll be able to place and set out piling create linear arrays
00:09
and work with model groups.
00:11
The objective domains covered are 1.1 a work with foundations and
00:22
A linear array can be used to set out piling with regular distances between pole
00:27
centers or used to distribute a required number of piles along an element's length.
00:33
When the linear Aral
00:34
is used, you have the option of grouping these elements together.
00:38
Therefore, if you make changes to the elements, setting out all the other groups,
00:41
objects would update
00:43
certain restrictions apply when grouping elements.
00:46
For example, if you have a pile that is located on a grid, by default,
00:51
the pile will move with grids.
00:53
If you then group the piles without the grid,
00:56
the relationship cannot be maintained.
00:60
Go ahead and open up the model 012,
01:03
work with structural foundations. Part two,
01:06
the model opens up in a 3d view.
01:10
Our first task is to place some piling along a ground beam
01:14
to do this. We're going to open up the top of foundation plan.
01:20
Let's zoom in to grid three.
01:22
And you'll notice on grid three,
01:23
we have this ground beam passing through this grid position.
01:28
Here,
01:29
we're going to place three piles into the ground beam and
01:32
then group those piles together and copy them to other locations.
01:36
So let's begin by clicking the structure ribbon
01:39
and then isolated
01:42
in the properties paddock
01:44
in the type selector,
01:45
ensure that you have round in situ concrete pile families selected.
01:49
And here we're going to use our 16 inch diameter, 16 ft long pile.
01:56
You'll notice in the properties pad that the level that this
01:59
is constrained to is negative 01 top of Found Ocean.
02:03
You'll also notice here that we have a height offset from level of minus 2 ft.
02:08
That's so our pile is set out on the soffit of our ground beam.
02:14
So now we can go ahead and place out our first pile.
02:18
I'll then place another one at an arbitrary position on this grid here
02:21
and another one to the left,
02:25
we can now use temporary dimensions to set out these piles.
02:29
So I'd like to try and maintain 2.5 times the piles diameter.
02:33
So in this case, that's going to equate to 40 inches.
02:37
I've selected this pile here.
02:39
You'll note that the temporary dimensions,
02:41
Witness line isn't attached to the correct element.
02:44
So I can simply drag this to the pile center.
02:47
And here
02:49
again, stipulate 40 inches.
02:53
So our piles are now set out the next step is to group these piles together.
02:59
Now,
02:59
one of the things we have to be mindful of is the first
03:01
pile that I placed down is positioned on this grid line here.
03:06
So consequently, when I group these together,
03:09
because the grid's not gonna be in the group rev, it will show a warning.
03:13
Let's go ahead and select our foundations. So I'm going to window select them
03:18
and then we'll use the filter
03:20
to remove the structural column.
03:22
So we've only got the three piles in the selection set.
03:27
Notice up on the context ribbon, I have the option of creating a group.
03:34
Now, as I've said here, you'll notice that these piles are currently set out on grid
03:39
here.
03:39
Rev It is informing us that a structured element will
03:41
be detached from the grid due to inconsistent group membership.
03:46
That's fine. We'll click OK here
03:48
and we can name the group. So I'm just going to call this 13 pile
03:53
setting out
03:58
and then click. OK.
04:01
Now you'll notice here that we can adjust the origin of our group.
04:05
I'm going to have this on the grid intersection.
04:11
OK.
04:12
So now that we have our group created,
04:14
we can then proceed to use the group to populate other grid intersections
04:19
to do this.
04:19
If we look in the project browser, we'll notice that we have a folder titled groups.
04:24
And here we have model groups.
04:27
Here's our group that we've just created.
04:29
I can simply drag and drop from the project browser
04:32
and then place the group down on another grid intersection.
04:38
If we now go into the 3D view and review our model in three dimensions,
04:43
we'll now see these piles in groups.
04:47
A nice property of a group is that if I want
04:50
to go ahead and perhaps change the length of these piles,
04:53
I can select the group
04:54
and on the context ribbon, I can edit the group.
04:58
Now,
04:59
it might be here that we have a requirement for the center pile to be slightly deeper.
05:03
So I've selected this pile here
05:06
in the properties padded in the type selector, I can use a 16 inch diameter pile.
05:10
But this time 24 ft long
05:14
note, when I click the finish tool over here,
05:18
all the groups update.
05:21
Now, if I didn't want them all to update, I could choose one of the groups
05:25
and I could perhaps
05:27
gro
05:27
this which will convert this back into three different elements.
05:34
Next, we're going to use an array to create a linear pattern of piles.
05:39
Let's open up the negative 02 lift pit plan
05:46
here, we're going to place some piling underneath this structural wall here.
05:51
Now, here we have a foundation slab which is 24 inches deep.
05:55
We need to make sure that the top of the pile is set down 24 inches.
05:59
So we're going to adjust the height offset from level of our pile.
06:04
So on the structure ribbon select isolated
06:10
notice here that we have our 16 inch diameter pile. Once again, it's 16 ft long
06:16
and we'll place our first pile on the intersection of these two walls.
06:22
But note here that we have a high offset from level of 2 ft.
06:28
OK. So I'm now going to array this pile so we can select the pile.
06:33
And on the context ribbon, we have the
06:36
areal.
06:37
Let's go ahead and select a ray
06:41
on the options bar. We have either a linear pattern or a radial pattern.
06:47
The default is a linear pattern
06:51
here, we can stipulate the number of items that we want in the array.
06:55
And here I'm going to move this to the second item
06:59
so I can snap to the original pile that I've placed down,
07:03
move my mouse to the right. And again, here I need to use 40 inches for our setting out.
07:11
So you can now see that we have our piling laid out. Currently, I only have two piles.
07:16
So here we can adjust this.
07:19
So perhaps we could set this to eight piles
07:22
and you can see that almost takes us to the edge of the wall.
07:25
Now, what I could do here is simply stretch out these piles.
07:28
So I have eight piles set out along the length of that wall.
07:31
If I wanted to do that, I could take the last pile here
07:35
and drag it. And you can see that it would snap to the center line of that wall,
07:40
our piling is now set out.
07:43
Now, once again, here, if we go into the 3d view,
07:46
we'll note that that piling now resides inside a group.
07:51
Of course, if I wanted to change the item inside the group there,
07:54
I could edit the group,
07:56
we could select the pile.
07:58
And as we saw previously, we could change the length perhaps to 24 ft
08:04
click finish.
08:06
And of course, all the piles update.
Video transcript
00:02
After completing this lesson,
00:03
you'll be able to place and set out piling create linear arrays
00:09
and work with model groups.
00:11
The objective domains covered are 1.1 a work with foundations and
00:22
A linear array can be used to set out piling with regular distances between pole
00:27
centers or used to distribute a required number of piles along an element's length.
00:33
When the linear Aral
00:34
is used, you have the option of grouping these elements together.
00:38
Therefore, if you make changes to the elements, setting out all the other groups,
00:41
objects would update
00:43
certain restrictions apply when grouping elements.
00:46
For example, if you have a pile that is located on a grid, by default,
00:51
the pile will move with grids.
00:53
If you then group the piles without the grid,
00:56
the relationship cannot be maintained.
00:60
Go ahead and open up the model 012,
01:03
work with structural foundations. Part two,
01:06
the model opens up in a 3d view.
01:10
Our first task is to place some piling along a ground beam
01:14
to do this. We're going to open up the top of foundation plan.
01:20
Let's zoom in to grid three.
01:22
And you'll notice on grid three,
01:23
we have this ground beam passing through this grid position.
01:28
Here,
01:29
we're going to place three piles into the ground beam and
01:32
then group those piles together and copy them to other locations.
01:36
So let's begin by clicking the structure ribbon
01:39
and then isolated
01:42
in the properties paddock
01:44
in the type selector,
01:45
ensure that you have round in situ concrete pile families selected.
01:49
And here we're going to use our 16 inch diameter, 16 ft long pile.
01:56
You'll notice in the properties pad that the level that this
01:59
is constrained to is negative 01 top of Found Ocean.
02:03
You'll also notice here that we have a height offset from level of minus 2 ft.
02:08
That's so our pile is set out on the soffit of our ground beam.
02:14
So now we can go ahead and place out our first pile.
02:18
I'll then place another one at an arbitrary position on this grid here
02:21
and another one to the left,
02:25
we can now use temporary dimensions to set out these piles.
02:29
So I'd like to try and maintain 2.5 times the piles diameter.
02:33
So in this case, that's going to equate to 40 inches.
02:37
I've selected this pile here.
02:39
You'll note that the temporary dimensions,
02:41
Witness line isn't attached to the correct element.
02:44
So I can simply drag this to the pile center.
02:47
And here
02:49
again, stipulate 40 inches.
02:53
So our piles are now set out the next step is to group these piles together.
02:59
Now,
02:59
one of the things we have to be mindful of is the first
03:01
pile that I placed down is positioned on this grid line here.
03:06
So consequently, when I group these together,
03:09
because the grid's not gonna be in the group rev, it will show a warning.
03:13
Let's go ahead and select our foundations. So I'm going to window select them
03:18
and then we'll use the filter
03:20
to remove the structural column.
03:22
So we've only got the three piles in the selection set.
03:27
Notice up on the context ribbon, I have the option of creating a group.
03:34
Now, as I've said here, you'll notice that these piles are currently set out on grid
03:39
here.
03:39
Rev It is informing us that a structured element will
03:41
be detached from the grid due to inconsistent group membership.
03:46
That's fine. We'll click OK here
03:48
and we can name the group. So I'm just going to call this 13 pile
03:53
setting out
03:58
and then click. OK.
04:01
Now you'll notice here that we can adjust the origin of our group.
04:05
I'm going to have this on the grid intersection.
04:11
OK.
04:12
So now that we have our group created,
04:14
we can then proceed to use the group to populate other grid intersections
04:19
to do this.
04:19
If we look in the project browser, we'll notice that we have a folder titled groups.
04:24
And here we have model groups.
04:27
Here's our group that we've just created.
04:29
I can simply drag and drop from the project browser
04:32
and then place the group down on another grid intersection.
04:38
If we now go into the 3D view and review our model in three dimensions,
04:43
we'll now see these piles in groups.
04:47
A nice property of a group is that if I want
04:50
to go ahead and perhaps change the length of these piles,
04:53
I can select the group
04:54
and on the context ribbon, I can edit the group.
04:58
Now,
04:59
it might be here that we have a requirement for the center pile to be slightly deeper.
05:03
So I've selected this pile here
05:06
in the properties padded in the type selector, I can use a 16 inch diameter pile.
05:10
But this time 24 ft long
05:14
note, when I click the finish tool over here,
05:18
all the groups update.
05:21
Now, if I didn't want them all to update, I could choose one of the groups
05:25
and I could perhaps
05:27
gro
05:27
this which will convert this back into three different elements.
05:34
Next, we're going to use an array to create a linear pattern of piles.
05:39
Let's open up the negative 02 lift pit plan
05:46
here, we're going to place some piling underneath this structural wall here.
05:51
Now, here we have a foundation slab which is 24 inches deep.
05:55
We need to make sure that the top of the pile is set down 24 inches.
05:59
So we're going to adjust the height offset from level of our pile.
06:04
So on the structure ribbon select isolated
06:10
notice here that we have our 16 inch diameter pile. Once again, it's 16 ft long
06:16
and we'll place our first pile on the intersection of these two walls.
06:22
But note here that we have a high offset from level of 2 ft.
06:28
OK. So I'm now going to array this pile so we can select the pile.
06:33
And on the context ribbon, we have the
06:36
areal.
06:37
Let's go ahead and select a ray
06:41
on the options bar. We have either a linear pattern or a radial pattern.
06:47
The default is a linear pattern
06:51
here, we can stipulate the number of items that we want in the array.
06:55
And here I'm going to move this to the second item
06:59
so I can snap to the original pile that I've placed down,
07:03
move my mouse to the right. And again, here I need to use 40 inches for our setting out.
07:11
So you can now see that we have our piling laid out. Currently, I only have two piles.
07:16
So here we can adjust this.
07:19
So perhaps we could set this to eight piles
07:22
and you can see that almost takes us to the edge of the wall.
07:25
Now, what I could do here is simply stretch out these piles.
07:28
So I have eight piles set out along the length of that wall.
07:31
If I wanted to do that, I could take the last pile here
07:35
and drag it. And you can see that it would snap to the center line of that wall,
07:40
our piling is now set out.
07:43
Now, once again, here, if we go into the 3d view,
07:46
we'll note that that piling now resides inside a group.
07:51
Of course, if I wanted to change the item inside the group there,
07:54
I could edit the group,
07:56
we could select the pile.
07:58
And as we saw previously, we could change the length perhaps to 24 ft
08:04
click finish.
08:06
And of course, all the piles update.
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in to start learning
Sign in for unlimited free access to all learning content.Save your progress
Take assessments
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.