Setting up proposed condition scenarios

Create child scenarios from existing scenarios in preparation for editing.


Tutorial resources

These downloadable resources will be used to complete this tutorial:


00:04

Once you set up various scenarios,

00:06

you can also create sub scenarios of

00:08

child scenarios that contain different conditions.

00:11

This allows you to analyze multiple alternatives

00:14

based on the conditions that you change.

00:17

In this exercise.

00:18

You set up three new proposed condition scenarios for annual average demands,

00:23

maximum day demands.

00:25

And the new pumping scheme,

00:27

these new proposed condition scenarios will be Children of the existing

00:32

E X max day and E X alt pumping scenarios respectively

00:38

to begin. Double click the desired project dot APR X file to open

00:42

Agis Pro.

00:44

Once the project starts,

00:45

click the info water pro tab to open the info water pro ribbon

00:51

in the project panel, click initialize

00:54

in the model explorer on the attribute tab, click the scenario explorer icon

01:01

in the scenario explorer under network data scenarios,

01:04

select the existing scenario and then in the toolbar click new scenario

01:11

in the new data scenario pop-up, assign a new id of 2030 to this sub scenario

01:16

and then click OK,

01:19

pipes will be added to this sub scenario.

01:21

So that proposed developments coming online by 2030 can be analyzed,

01:26

repeat this process for the next

01:29

day scenario

01:31

in the network data scenario section, select the

01:34

max day scenario.

01:36

Click new scenario,

01:39

assign a new id of 2030 underscore max day and click. OK.

01:44

This sub scenario will analyze the anticipated

01:51

Once more. Back in the network data scenario section, select the

01:56

alt pumping scenario.

01:58

Click new scenario,

02:00

assign a new id of 2030 underscore alt pumping

02:04

and then click. OK.

02:06

This sub scenario will analyze the anticipated 2030

02:10

facilities under the proposed new pumping operations.

02:14

These 2030 sub scenarios are now ready to be edited,

02:18

click exit to close the scenario explorer.

Video transcript

00:04

Once you set up various scenarios,

00:06

you can also create sub scenarios of

00:08

child scenarios that contain different conditions.

00:11

This allows you to analyze multiple alternatives

00:14

based on the conditions that you change.

00:17

In this exercise.

00:18

You set up three new proposed condition scenarios for annual average demands,

00:23

maximum day demands.

00:25

And the new pumping scheme,

00:27

these new proposed condition scenarios will be Children of the existing

00:32

E X max day and E X alt pumping scenarios respectively

00:38

to begin. Double click the desired project dot APR X file to open

00:42

Agis Pro.

00:44

Once the project starts,

00:45

click the info water pro tab to open the info water pro ribbon

00:51

in the project panel, click initialize

00:54

in the model explorer on the attribute tab, click the scenario explorer icon

01:01

in the scenario explorer under network data scenarios,

01:04

select the existing scenario and then in the toolbar click new scenario

01:11

in the new data scenario pop-up, assign a new id of 2030 to this sub scenario

01:16

and then click OK,

01:19

pipes will be added to this sub scenario.

01:21

So that proposed developments coming online by 2030 can be analyzed,

01:26

repeat this process for the next

01:29

day scenario

01:31

in the network data scenario section, select the

01:34

max day scenario.

01:36

Click new scenario,

01:39

assign a new id of 2030 underscore max day and click. OK.

01:44

This sub scenario will analyze the anticipated

01:51

Once more. Back in the network data scenario section, select the

01:56

alt pumping scenario.

01:58

Click new scenario,

02:00

assign a new id of 2030 underscore alt pumping

02:04

and then click. OK.

02:06

This sub scenario will analyze the anticipated 2030

02:10

facilities under the proposed new pumping operations.

02:14

These 2030 sub scenarios are now ready to be edited,

02:18

click exit to close the scenario explorer.

Step-by-step:

Once you set up various scenarios, you can also create sub-scenarios of child scenarios that contain different conditions. This allows you to analyze multiple alternatives based on the conditions that you change.

In this tutorial, you set up three new proposed condition scenarios for annual average demands, maximum day demands, and the new pumping scheme. These new proposed condition scenarios will be children of the EXISTING, EX_MAXDAY, and EX_ALTPUMPING scenarios, respectively.

  1. Open the appropriate .aprx file in ArcGIS Pro.
  2. From the ribbon, InfoWater Pro tab, Project panel, click Initialize.
  3. In the Model Explorer, click the Scenario Explorer icon.
    Model Explorer with Scenario Explorer icon highlighted
  1. In the Scenario Explorer, under Network Data Scenario(s), select the EXISTING scenario.
  2. In the toolbar, click New Scenario.
    Scenario Explorer with EXISTING scenario selected and New Scenario highlighted in the toolbar
  1. In the New Data Scenario popup, assign a New ID of 2030 to this sub-scenario, and then click OK.

Pipes will be added to this sub-scenario so that proposed developments coming online by 2030 can be analyzed.

  1. Repeat steps 4 – 6 for the EX_MAXDAY scenario:
    1. In the Network Data Scenario(s) section, select the EX_MAXDAY scenario.
    2. From the toolbar, click New Scenario.
    3. In the New Data Scenario popup, assign a New ID of “2030_MAXDAY”.
    4. Click OK.

This sub-scenario will analyze the anticipated 2030 facilities under a maximum day condition.

  1. Repeat steps 4 – 6 for the EX_ALTPUMPING scenario:
    1. In the Network Data Scenario(s) section, select the EX_ALTPUMPING scenario.
    2. From the toolbar, click New Scenario.
    3. In the New Data Scenario popup, assign a New ID of “2030_ALTPUMPING”.
    4. Click OK.

This sub-scenario will analyze the anticipated 2030 facilities under the proposed new pumping operations.

  1. These 2030 sub-scenarios are now ready to be edited:
    Scenario Explorer with the three new 2030 sub-scenarios highlighted
  2. Click Exit to close the Scenario Explorer.