& Construction
Integrated BIM tools, including Revit, AutoCAD, and Civil 3D
& Manufacturing
Professional CAD/CAM tools built on Inventor and AutoCAD
Optimize SuDS features in a drainage system model for analysis.
Tutorial resources
These downloadable resources will be used to complete this tutorial:
Once you have modeled a fully featured drainage system with SuDS, you are ready to simulate how they operate during rainfall events.
Once the simulation is complete, the Stormwater Controls Summary dialog box opens. In this example, it shows the results of the first 15-minute summer storm. Realize that there are a total of 18 storms that were used throughout the creation of this model.
In this example, three different storms were the critical duration for the three stormwater controls.
The Percentage Available (%) column shows the percentage of the total volume of the Stormwater Control available above the maximum water elevation measured to the exceedance elevation. A negative value shows that the capacity of the storage structure has been exceeded. Here, the pond has 39% of its capacity available. This is not surprising, because the introduction of the two SuDS structures to this model has reduced the flow rate into the pond. Now, you will be able to reduce its size substantially.
The swale is at minus 5%, meaning that it is a little undersized. However, the size of the swale is fixed, so instead, you need to increase the discharge rate from the swale so that its capacity is acceptable.
You can apply a similar approach to the cellular storage. It is currently at plus 8%, so its pass forward rate can be reduced a little.
Once you have optimized the upstream SuDS, you can reassess the pond.
Best practice is to create a new phase for the SuDS optimization:
Note that, back in the Cellular Storage dialog box, a new Diameter of 58 mm was calculated.
In this example, the swale and cellular storage capacities are now optimized to within 2% of capacity, but the pond is on 39% and therefore needs further optimization.
The Stormwater Controls Summary shows that the maximum resident volume in the pond is 485 meters cubed. A top tip is to size the pond slightly smaller than this value. In this case, it was determined that 385 meters cubed is the right size for the pond.
In this example, the flow path reveals no broken connections.
There is zero percent available, but the Status is OK. The maximum resident volume is 384 meters cubed, so less than 1 meter cubed is available. In reality, you may need to increase the size of the pond slightly, but for this exercise, it is perfectly optimized.