Creating a rebar partition schedule

Creating a Rebar Partition Schedule

This is getting easy! So suppose we want to just basically group and categorize rebar into an area. For example, we want to designate all of our rebar in Pier 1, but since there are really two piers for P-1 we want to group it into P1-A and P1-B

  • Open the model you have been working in.
  • Go to the PIER-1 PLAN DETAIL view.

     Pick a window around all of the rebar in the south pier as shown, selecting all of the bars in that pier.

In the Properties, in the Partition row, add P1-A

Select the rebar in the north pier and add them to the Partition P1-B.

In the Project Browser, scroll down to Schedules/Quantities (all)

Right click on the REBAR LENGTH SCHEDULE

  • Select Duplicate View
  • Select Duplicate

  • Rename it to PARTITION SCHEDULE
  • In the partition schedule Properties, click the Edit button next to Fields

  • Find Partition and add it to the column on the right
  • Click the Move parameter up button to put it at the top

  • Go to the Sorting/Grouping tab
  • Change Sort By: to Partition
  • Check on Footer
  • Check on Itemize every instance

 

  • Click OK
  • Your schedule should look like the image below: