00:03
Rivet panel schedules are very useful
00:06
for capturing and verifying circuit information
00:09
and for driving changes in a project such as circuit and phase allocation,
00:14
the information contained in a panel schedule and the format
00:17
of the presentation is determined by a panel schedule templates
00:21
and those templates are part of the overall
00:24
project template.
00:26
The existing panel schedule templates can be
00:28
customized or duplicated to create additional templates.
00:32
For customization.
00:34
In this project,
00:35
we will review an existing panel schedule and then create a
00:39
duplicate of an existing template and investigate the presentation options.
00:44
After applying some changes,
00:46
the new panel schedule template will be introduced to the
00:49
project and used in place of the existing one.
00:54
Let's open and review the panel schedule for LP two.
00:59
There is a section at the top for entering text notes.
01:04
The schedule has a fixed number of single pole breakers currently set at 42
01:10
values have been added for the circuits connected to this panel
01:16
and the loads classifications are listed with values total at the bottom.
01:22
Because most of the information on the panel
01:24
schedule comes from the circuits in the project,
01:26
it's automatically populated and therefore updated
01:30
as the circuits are created and modified
01:33
from the manage tab of the ribbon.
01:35
Select the panel schedule templates, dropdown menu and select
01:40
manage templates
01:43
from here. Create a duplicate of the branch panel
01:50
and rename it branch panel commercial,
01:57
then select the new panel and make it the default.
02:02
All new panel schedules will now be created from this panel schedule template.
02:07
And any existing schedules can be set to use the new standard
02:11
select, OK. To close the window
02:15
from the manage tab of the ribbon, select the panel schedule templates,
02:19
dropdown menu
02:22
and select edit a template,
02:26
select and open the new template.
02:30
Let's start by editing the template to display
02:33
the number of elements on each circuit,
02:37
select the column
02:38
headed trip
02:39
and from the ribbon choose insert column
02:43
left of selected
02:47
a new column has now been added to either side and some adjustment is required
02:51
use the grips to alter the column width,
02:59
highlight the entire column to the left
03:02
and from the ribbon. Select edit borders,
03:08
then pick outside and inside
03:14
and repeat for the column on the other side of the template.
03:20
Next, we will add the parameter that will automatically complete this field.
03:25
When the panel schedule is in use,
03:28
select the first field below the column head.
03:31
Then from the parameters panel, select the add parameter,
03:35
dropdown menu and choose number of elements,
03:42
select the text in the column head and
03:45
edit the title to number of connected elements.
03:54
Then
03:55
set each of the cells to center, horizontal alignment
04:03
and bottom vertical alignment.
04:09
Finally edit the font to make the text bold to match the rest of the column heads
04:28
from the ribbon select set template options
04:32
in the general settings,
04:33
we see the value for the number of slots that will be displayed in the panel schedule,
04:38
change the option to variable so that the schedule will only show
04:41
the number assigned to the panel rather than the number set here.
04:46
The options found in circuit table include the column header, text orientation
04:53
and the format in which the loads will be presented in the panel schedule.
04:59
Leave this set to loads in split columns by phase.
05:04
And finally, options for the display of unused phases.
05:08
For panels that are not three phase
05:12
within the load summary area,
05:14
we can decide whether to show in the panel schedule
05:17
only the loads that are connected to the panel.
05:19
In which case, all loads in the right hand column are considered.
05:23
And in the order set by using the move up and move down options
05:28
or a constant set of load classifications.
05:31
In this case,
05:32
we can choose which loads are to be included and
05:35
in which order they will appear in the finished panel schedule
05:40
select, ok to close the window,
05:43
select finish template from the template, editor panel to return to the project
05:51
to apply the new template, select change template from the ribbon,
05:57
select the commercial template and choose OK,
06:03
read the message and select a yes.
06:07
The new template has been applied
06:10
and the change is clear to see,
06:12
select the panel schedule from the screen
06:16
and edit the property for the maximum number of single pole breakers to 24
06:25
and see the panel schedule update accordingly.
06:29
Editing an existing or duplicated panel schedule,
06:32
gives you access to a range of presentation options to
06:35
suit your preference for the appearance of panel schedules.
06:39
A standard which can be used across multiple projects and delivery teams
06:44
from additional fields of data to the general display of information,
06:48
creating custom panel schedules can assist in the way electrical distribution is
06:52
reviewed and can improve the clarity of important information in your project.
Video transcript
00:03
Rivet panel schedules are very useful
00:06
for capturing and verifying circuit information
00:09
and for driving changes in a project such as circuit and phase allocation,
00:14
the information contained in a panel schedule and the format
00:17
of the presentation is determined by a panel schedule templates
00:21
and those templates are part of the overall
00:24
project template.
00:26
The existing panel schedule templates can be
00:28
customized or duplicated to create additional templates.
00:32
For customization.
00:34
In this project,
00:35
we will review an existing panel schedule and then create a
00:39
duplicate of an existing template and investigate the presentation options.
00:44
After applying some changes,
00:46
the new panel schedule template will be introduced to the
00:49
project and used in place of the existing one.
00:54
Let's open and review the panel schedule for LP two.
00:59
There is a section at the top for entering text notes.
01:04
The schedule has a fixed number of single pole breakers currently set at 42
01:10
values have been added for the circuits connected to this panel
01:16
and the loads classifications are listed with values total at the bottom.
01:22
Because most of the information on the panel
01:24
schedule comes from the circuits in the project,
01:26
it's automatically populated and therefore updated
01:30
as the circuits are created and modified
01:33
from the manage tab of the ribbon.
01:35
Select the panel schedule templates, dropdown menu and select
01:40
manage templates
01:43
from here. Create a duplicate of the branch panel
01:50
and rename it branch panel commercial,
01:57
then select the new panel and make it the default.
02:02
All new panel schedules will now be created from this panel schedule template.
02:07
And any existing schedules can be set to use the new standard
02:11
select, OK. To close the window
02:15
from the manage tab of the ribbon, select the panel schedule templates,
02:19
dropdown menu
02:22
and select edit a template,
02:26
select and open the new template.
02:30
Let's start by editing the template to display
02:33
the number of elements on each circuit,
02:37
select the column
02:38
headed trip
02:39
and from the ribbon choose insert column
02:43
left of selected
02:47
a new column has now been added to either side and some adjustment is required
02:51
use the grips to alter the column width,
02:59
highlight the entire column to the left
03:02
and from the ribbon. Select edit borders,
03:08
then pick outside and inside
03:14
and repeat for the column on the other side of the template.
03:20
Next, we will add the parameter that will automatically complete this field.
03:25
When the panel schedule is in use,
03:28
select the first field below the column head.
03:31
Then from the parameters panel, select the add parameter,
03:35
dropdown menu and choose number of elements,
03:42
select the text in the column head and
03:45
edit the title to number of connected elements.
03:54
Then
03:55
set each of the cells to center, horizontal alignment
04:03
and bottom vertical alignment.
04:09
Finally edit the font to make the text bold to match the rest of the column heads
04:28
from the ribbon select set template options
04:32
in the general settings,
04:33
we see the value for the number of slots that will be displayed in the panel schedule,
04:38
change the option to variable so that the schedule will only show
04:41
the number assigned to the panel rather than the number set here.
04:46
The options found in circuit table include the column header, text orientation
04:53
and the format in which the loads will be presented in the panel schedule.
04:59
Leave this set to loads in split columns by phase.
05:04
And finally, options for the display of unused phases.
05:08
For panels that are not three phase
05:12
within the load summary area,
05:14
we can decide whether to show in the panel schedule
05:17
only the loads that are connected to the panel.
05:19
In which case, all loads in the right hand column are considered.
05:23
And in the order set by using the move up and move down options
05:28
or a constant set of load classifications.
05:31
In this case,
05:32
we can choose which loads are to be included and
05:35
in which order they will appear in the finished panel schedule
05:40
select, ok to close the window,
05:43
select finish template from the template, editor panel to return to the project
05:51
to apply the new template, select change template from the ribbon,
05:57
select the commercial template and choose OK,
06:03
read the message and select a yes.
06:07
The new template has been applied
06:10
and the change is clear to see,
06:12
select the panel schedule from the screen
06:16
and edit the property for the maximum number of single pole breakers to 24
06:25
and see the panel schedule update accordingly.
06:29
Editing an existing or duplicated panel schedule,
06:32
gives you access to a range of presentation options to
06:35
suit your preference for the appearance of panel schedules.
06:39
A standard which can be used across multiple projects and delivery teams
06:44
from additional fields of data to the general display of information,
06:48
creating custom panel schedules can assist in the way electrical distribution is
06:52
reviewed and can improve the clarity of important information in your project.
Create, edit, and apply panel schedule templates.
A new column is added to both sides of the panel schedule template.
All data fields in both new columns autofill.
To apply the new template to the project:
The panel schedule updates accordingly.
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in for the best experience
Save your progress
Get access to courses
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.