& Construction

Integrated BIM tools, including Revit, AutoCAD, and Civil 3D
& Manufacturing

Professional CAD/CAM tools built on Inventor and AutoCAD
Integrated BIM tools, including Revit, AutoCAD, and Civil 3D
Professional CAD/CAM tools built on Inventor and AutoCAD
Understand and create conceptual duct and pipe layouts.
Type:
Tutorial
Length:
4 min.
Tutorial resources
These downloadable resources will be used to complete this tutorial:
Transcript
00:04
At the early stages of an mep project to create a
00:07
detailed mechanical layout can be time
00:10
consuming costly and most likely unnecessary
00:14
with duct and pipe sizes, fittings and detailed coordination.
00:18
Something to be considered at a later stage.
00:22
Single line, indicative mechanical layouts are more usual at this stage.
00:27
Moving to detailed design as the project progresses
00:32
in red,
00:32
this is taken care of by using duct and pipe placeholders,
00:37
duct and pipe placeholders carry the same intelligence as regular duct and pipe
00:41
but are represented by a single line and do not consider details such as fittings,
00:49
duct and pipe placeholders are found on the
00:51
rack panel and the plumbing and piping panel of the systems tab
00:56
ensure the current view is set to H VAC floor plans one mec.
01:03
In this view, the equipment has been placed only as a guide.
01:08
Let's start by creating a duct placeholder,
01:11
select duck placeholder from the ribbon.
01:13
And a review of the type selector shows that even though this is a placeholder,
01:18
the duck type can still be selected
01:21
and from the options bar, the size can be set,
01:24
giving you the option to make an early choice if required
01:28
changing the system type to supply air,
01:31
leave all other options as they are and draw
01:34
a duct run along the center of the corridor
01:36
at a nominal height of 9 ft.
01:39
Then at the riser,
01:41
change the elevation to zero and select apply from the options bar,
01:48
set the elevation back to 9 ft and draw branches to each of the phone
01:53
call units.
01:55
At the last two fan call units, draw a duct placeholder that crosses the main run
02:12
from the plumbing and piping panel. Select pipe placeholder
02:17
and changing the system type to chilled water flow.
02:20
Draw a run along the corridor below the supply duct run
02:24
again at a height of 9 ft.
02:27
Then at the riser change the elevation to zero
02:30
and select apply
02:37
follow the same procedure to create a pipe placeholder for chilled water return,
02:42
changing the elevation to zero at the riser.
02:49
Finally create branch pipes from the main run for chilled water flow and
02:54
for chilled water to return to each of the fan core unit positions
02:59
at a height of 9 ft.
03:05
Quick,
03:05
conceptual mechanical layouts can be created without the
03:09
need to consider final pipe and duct sizes
03:12
associated fittings, final elevations or detailed coordination.
03:20
Although it isn't necessary to set and change elevations while
03:24
creating an early stage layout using duct and pipe placeholders.
03:29
A view of this 3D model can indicate the intentions more clearly.
Video transcript
00:04
At the early stages of an mep project to create a
00:07
detailed mechanical layout can be time
00:10
consuming costly and most likely unnecessary
00:14
with duct and pipe sizes, fittings and detailed coordination.
00:18
Something to be considered at a later stage.
00:22
Single line, indicative mechanical layouts are more usual at this stage.
00:27
Moving to detailed design as the project progresses
00:32
in red,
00:32
this is taken care of by using duct and pipe placeholders,
00:37
duct and pipe placeholders carry the same intelligence as regular duct and pipe
00:41
but are represented by a single line and do not consider details such as fittings,
00:49
duct and pipe placeholders are found on the
00:51
rack panel and the plumbing and piping panel of the systems tab
00:56
ensure the current view is set to H VAC floor plans one mec.
01:03
In this view, the equipment has been placed only as a guide.
01:08
Let's start by creating a duct placeholder,
01:11
select duck placeholder from the ribbon.
01:13
And a review of the type selector shows that even though this is a placeholder,
01:18
the duck type can still be selected
01:21
and from the options bar, the size can be set,
01:24
giving you the option to make an early choice if required
01:28
changing the system type to supply air,
01:31
leave all other options as they are and draw
01:34
a duct run along the center of the corridor
01:36
at a nominal height of 9 ft.
01:39
Then at the riser,
01:41
change the elevation to zero and select apply from the options bar,
01:48
set the elevation back to 9 ft and draw branches to each of the phone
01:53
call units.
01:55
At the last two fan call units, draw a duct placeholder that crosses the main run
02:12
from the plumbing and piping panel. Select pipe placeholder
02:17
and changing the system type to chilled water flow.
02:20
Draw a run along the corridor below the supply duct run
02:24
again at a height of 9 ft.
02:27
Then at the riser change the elevation to zero
02:30
and select apply
02:37
follow the same procedure to create a pipe placeholder for chilled water return,
02:42
changing the elevation to zero at the riser.
02:49
Finally create branch pipes from the main run for chilled water flow and
02:54
for chilled water to return to each of the fan core unit positions
02:59
at a height of 9 ft.
03:05
Quick,
03:05
conceptual mechanical layouts can be created without the
03:09
need to consider final pipe and duct sizes
03:12
associated fittings, final elevations or detailed coordination.
03:20
Although it isn't necessary to set and change elevations while
03:24
creating an early stage layout using duct and pipe placeholders.
03:29
A view of this 3D model can indicate the intentions more clearly.
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in for the best experience
Save your progress
Get access to courses
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.