Perform a GMR for a pipe break assessment.
Type:
Tutorial
Length:
6 min.
Tutorial resources
These downloadable resources will be used to complete this tutorial:
Transcript
00:03
This example is going to work through the configuration and simulation of a GMR.
00:08
For a pipe brake assessment.
00:10
You will configure the GMR to break each pipe
00:13
one by one and run a simulation for each bra
00:17
to begin open a network and control in the background.
00:22
Then in the model group window, right,
00:24
click generalized multi run group and select new generalized multi run config
00:31
a new name dialogue displays
00:33
for this example, set the name to pipe break assessment and then click OK.
00:40
A new generalized multi run appears in the model group window,
00:43
right? Click pipe brake assessment and select open
00:47
within the generalized multi run configuration dialogue.
00:50
Navigate to the test cases tab
00:53
from the model group dragon drop the pipes selection list into the selection list,
00:57
pane
00:58
expand the object type dropdown and choose pipe control.
01:04
Then in the grid scroll down to brake enabled and turn this on.
01:10
Then set the break start time to eight o'clock
01:14
and the break end time to nine o'clock.
01:17
Lastly set the brake type to rupture
01:22
in the test case name field. Enter a name to be used for all test cases,
01:27
insert pipe in the test case name and then enable the append
01:31
object ID to test case name. Option.
01:34
Click add to populate the table with test cases.
01:38
Next, click the results tab,
01:41
select keep all TVD results and individual summaries,
01:45
click the analysis tab and select use stored query
01:51
from the model group.
01:52
Expand the stored query group and drag the CP
01:55
less than 20 m SQL into the stored query pane
01:59
set the query time to be 25 2022 at nine o'clock
02:05
from the model group, right, click run group and select new
02:09
run
02:11
name this run pipe brake assessment in the schedule,
02:14
hydraulic run dialogue and then set the run to experimental
02:19
in the schedule. Hydraulic run dialogue.
02:21
Ensure a network control and demand diagram are assigned,
02:26
expand the run type dropdown and select normal.
02:31
Then from the run type group, select generalized multi run
02:37
from the generalized multi run options.
02:39
Dialogue specify the previously created pipe
02:42
break assessment configuration by dragging it
02:44
from the model group and dropping it into the configuration pane.
02:48
Or you could select browse navigate to the configuration you want
02:53
and select it.
02:55
Click ok
02:57
back in the schedule. Hydraulic run dialogue, click run
03:02
after a few minutes. The run displays in the model group window,
03:07
you will notice a number of simulations are present as well as the summary report.
03:14
The simulations are those that have met the criteria specified in the stored query.
03:19
Right? Click the control simulation
03:22
and select open as
03:24
summary report,
03:26
a summary report appears that includes a summary of each
03:29
test case where the maximum pressure is below 20 m.
03:33
It also includes columns for the minimum average and maximum
03:37
pressures as well as the id of the customer point.
03:40
It occurs at
03:41
this data represents the constraints you applied through
03:44
the CP less than 20 m stored query.
03:48
Right click one of the test case simulations
03:51
from here, you can open this as a summary that is specific to that simulation
03:56
or you can open it as simulation results on the
03:59
GEO plan and apply any themes or labeling necessary.
Video transcript
00:03
This example is going to work through the configuration and simulation of a GMR.
00:08
For a pipe brake assessment.
00:10
You will configure the GMR to break each pipe
00:13
one by one and run a simulation for each bra
00:17
to begin open a network and control in the background.
00:22
Then in the model group window, right,
00:24
click generalized multi run group and select new generalized multi run config
00:31
a new name dialogue displays
00:33
for this example, set the name to pipe break assessment and then click OK.
00:40
A new generalized multi run appears in the model group window,
00:43
right? Click pipe brake assessment and select open
00:47
within the generalized multi run configuration dialogue.
00:50
Navigate to the test cases tab
00:53
from the model group dragon drop the pipes selection list into the selection list,
00:57
pane
00:58
expand the object type dropdown and choose pipe control.
01:04
Then in the grid scroll down to brake enabled and turn this on.
01:10
Then set the break start time to eight o'clock
01:14
and the break end time to nine o'clock.
01:17
Lastly set the brake type to rupture
01:22
in the test case name field. Enter a name to be used for all test cases,
01:27
insert pipe in the test case name and then enable the append
01:31
object ID to test case name. Option.
01:34
Click add to populate the table with test cases.
01:38
Next, click the results tab,
01:41
select keep all TVD results and individual summaries,
01:45
click the analysis tab and select use stored query
01:51
from the model group.
01:52
Expand the stored query group and drag the CP
01:55
less than 20 m SQL into the stored query pane
01:59
set the query time to be 25 2022 at nine o'clock
02:05
from the model group, right, click run group and select new
02:09
run
02:11
name this run pipe brake assessment in the schedule,
02:14
hydraulic run dialogue and then set the run to experimental
02:19
in the schedule. Hydraulic run dialogue.
02:21
Ensure a network control and demand diagram are assigned,
02:26
expand the run type dropdown and select normal.
02:31
Then from the run type group, select generalized multi run
02:37
from the generalized multi run options.
02:39
Dialogue specify the previously created pipe
02:42
break assessment configuration by dragging it
02:44
from the model group and dropping it into the configuration pane.
02:48
Or you could select browse navigate to the configuration you want
02:53
and select it.
02:55
Click ok
02:57
back in the schedule. Hydraulic run dialogue, click run
03:02
after a few minutes. The run displays in the model group window,
03:07
you will notice a number of simulations are present as well as the summary report.
03:14
The simulations are those that have met the criteria specified in the stored query.
03:19
Right? Click the control simulation
03:22
and select open as
03:24
summary report,
03:26
a summary report appears that includes a summary of each
03:29
test case where the maximum pressure is below 20 m.
03:33
It also includes columns for the minimum average and maximum
03:37
pressures as well as the id of the customer point.
03:40
It occurs at
03:41
this data represents the constraints you applied through
03:44
the CP less than 20 m stored query.
03:48
Right click one of the test case simulations
03:51
from here, you can open this as a summary that is specific to that simulation
03:56
or you can open it as simulation results on the
03:59
GEO plan and apply any themes or labeling necessary.
To simulate a pipe break and assess the results, first configure the GMR to break each pipe one by one. Then, run a simulation for each break.
A new Generalized Multi Run appears in the Model Group window:
The table populates with the Pipes test cases:
After a few minutes, the run displays in the Model Group window:
Note: There are a number of simulations present, as well as the summary report. The simulations are those that have met the criteria specified in the stored query.
A Summary Report appears that includes a summary of each test case where the maximum pressure is below 20m:
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in for the best experience
Save your progress
Get access to courses
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.